ACI Concrete Test| Questions and 100% Correct Answers| Latest Update

Document preview thumbnail
Preview 3 out of 18 pages

ACI Concrete Test| Questions and 100% Correct Answers| Latest Update

Content preview

ACI Concrete Test| Questions and 100%
Correct Answers| Latest Update

What needs to be done if the concrete contains aggregate larger than the appropriate size of
the molds or equipment being used - ANSWER Wet-sieve the sample


It is good to _______ concrete before any test - ANSWER Re-mix


Regulate the rate of discharge of the concrete by the ____ __ ____________ of the drumb and
not by the size of the gate opening - ANSWER Rate of Revolution


What procedures are required between taking the sample from the mixer and preforming tests

a) transport to place where tests will be preformed
b) combine and remix with a shovel
c) both a & b
d) Grab sample from the top - ANSWER c) both a & b


If sampling from a concrete pump
a) Always obtain sample at point of placement (end of line pump)
b) always sample from the mixed before the concrete is discharge in the pump hopper
c) always pick the easiest and safest way possible

d) specifications may determine points of sampling - ANSWER d) specifications may
determine points of sampling

,When strength tests are requires, the minumum sample size of the sample will be - ANSWER 1
cubic foot



how large is a slump mold - ANSWER 4 inches to the top diameter, 8 inches bottom diameter
, and 12 inches high


How long should you complete the slump test in - ANSWER 2 and a half mins


Fill the mold in 3 approximately equal layers by ___________ - ANSWER Volume


Rod each layer of the slump mold ____ times - ANSWER 25


when rodding, penetrate previous layer approximately how deep - ANSWER 1 inch



With one smooth motion without twisting the mold Raise the mold how many seconds -
ANSWER 5 plus or minus 2 seconds


Measure slump to the nearest _____ inch - ANSWER 1/4


Measure the from the top of the cone to the _________ ________ of the concrete - ANSWER
Displaced center


Container size depends on - ANSWER Maximum normal aggregate



When do you need to choose to rod or vibrate concrete - ANSWER Rod when greater than
3 inches; optional between 1 - 3 inches; vibrate if less than 1 inch



When filling the air meter the concrete should have an excess of how many inches - ANSWER
1/8th

, Define relative yield - ANSWER Ratio of the actual volume of concrete obtained, to the
volume designed for the batch


Aggregates must be _______ dense or __________ - ANSWER Relatively dense; normal


Never continue vibration long enough to cause the escape of ______ from a sample - ANSWER
Froth



If water enters the air chamber on a Pressure method it must be - ANSWER - bled from the
air chamber through the bleeded valve followed by several strokes of the pump
- Pressure released by opening both petcocks before removing the cover


Volumetric method can be used for _______ of aggregate - ANSWER any type


Tapping the side of concrete molds can be done with both.... - ANSWER a rubber mallet or an
open hand


Where do you mark the concrete specimen molds?T - ANSWER On the sides not on the cap



In standard initial curing Immediately store the specimens for up to 48 hours in a temperature
range between __ and __ degrees Fahrenheit - ANSWER 60 and 80



Upon completion of initial curing and within 30 mins after removing the molds from the
concrete, you must cure all speciments with free water maintained on tehir surfaces at all
times at a temperature of ______degrees F plus or minus ____ degrees F - ANSWER 73.5 plus
or minus 3.5


Max aggregate for slump test - ANSWER 1.5"

Document information

Uploaded on
September 5, 2024
Number of pages
18
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$13.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
KenAli
2.6
(18)
Sold
114
Followers
5
Items
24709
Last sold
2 weeks ago




Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”