FDOT Asphalt Paving Level 1EXAM QUESTIONS AND SOLUTIONS Random sampling - ANSWER Are random numbers generated usually by a VT for cores to be extracted from the roadway How often should you calibrate a Straight edge - ANSWER Calibrate at the start of each working period Using the manual straight edge you find what kind of spot to place the rolling straightedge? - ANSWER Locate a flat area with the manual straightedge and place the rolling straightedge next to the manual straightedge and the gauge should read 0 The 3/16 and the 3/8 shims go under which wheels during calibration - ANSWER The outside wheels to measure the low and the center to measure the high. Gauge should read 3/16 on the 3/16 shim and vice versa for the 3/8 shims. Make sure the center wheel moves up and down freely. Calibration materials for Straightedge - ANSWER Rolling Straightedge Manual Straightedge Manual Measurement (ruler) x4 3/16 shims 5mm thick x4 3/8 shims 10mm thick When to perform final straightedge - ANSWER After an entire lane has been paved When to perform final straightedge - ANSWER Pavement should be an ambient temperature You cannot use the straightedge until it has been properly - ANSWER calibrated When performing the straightedge procedure - ANSWER Maintain proper traffic management and safety Cross slopes can be either done - ANSWER Manually or with a smart level When using a manual cross slope you first - ANSWER Place a simple level on pavement After placing the simple level on the pavement then you - ANSWER Raise the down end of the level until it is level (bubble center) After the simple level is lifted until it is level you measure what - ANSWER The length of the simple level and the height between the (previously down) end of the level to the pavement Formula to calculate the manual cross slope - ANSWER Calculate the slope using the formula ( h / l ) x 100 = slope % Requirements for the rolling Straightedge - ANSWER Must have a read out gauge, kept clean and in working order, low and high reading, and marks to the nearest 1/16 (1mm) Rolling Straightedge pulled at - ANSWER 3 to 5mph or less Deficiencies pointed out with rolling straightedge you should first - ANSWER Mark the pavement at the center wheel where the needle initially shows a deficiency and where is ends. Also record location and measurements of deficiency. Core sampling is used for - ANSWER testing density and permeability Core sampling equipment - ANSWER Concrete saw Diamond bit core drill Size of core depends on test Ice chest (Optional) Ice (Optional) Asphalt to patch hole During core sampling the barrel should always be - ANSWER perpendicular to pavement Core sampling patching - ANSWER Fill hole with patch mix, if in lifts tamp each lift Storing cores - ANSWER Store in ice chest with bagged ice on top or put in an air conditioned cab Best stored upright in a cool place DO NOT THROW INTO PICKUP Determine Bulk Specific gravity on sampled cores - ANSWER Trim to correct lift Weigh dry sample if dry otherwise Place in water (77+-2) for 4+-1 minute Then roll within five seconds to achieve SSD weight Then dry to a constant weight with fan or core dryer Bulk Specific Gravity formula - ANSWER dry / SSD - water weight = BSG Asphalt Temperature Heat and Cold - ANSWER Too hot cooks asphalt Too cold can't compact The hole for temping asphalt trucks should be located where - ANSWER Hole located in the middle third of length of truck; 6-10 inches above the bed Temping asphalt on the top - ANSWER At engineer's discretion S to N - ANSWER Downstation W to E - ANSWER Downstation Stationing - ANSWER Starts at 0+00 Stationing Measurement - ANSWER 1+00 is 100 feet Straight Edge is the - ANSWER Measurement of Pavement smoothness with a 15 foot 4.573 m rolling straightedge Straight Edge is used to - ANSWER identify problems Asphalt Temperature Master Range - ANSWER +-30; reject loads outside Temp every load monitored if - ANSWER Mix within master range Differes for a single load from established temp by +-25°F Avg of five loads differes by +-15°F Monitor until within tolerance Tack Distributor without a calibration chart - ANSWER If they don't have a calibration chart you can not use them to distribute tack Application rate of tack for close graded mixes - ANSWER Normal: 0.02-0.08 gal/yd^2 Must apply temperature correction factor Calibration chart for distributor of tack - ANSWER Must be done by a reliable and recognized firm Chart provided to engineer prior to use Know the temperature of asphalt cement being used for Tack coat Measuring tack levels - ANSWER Stick the distributor before and after spraying tack Use calibration chart for Distributor to determine amount of asphalt in truck before and after spraying Formula for finding the length of a tacked road - ANSWER Find length of tacked road Station - station = station lineal feet

Content preview

FDOT Asphalt Paving Level 1EXAM
QUESTIONS AND SOLUTIONS
Random sampling - ANSWER Are random numbers generated usually by a VT for
cores to be extracted from the roadway

How often should you calibrate a Straight edge - ANSWER Calibrate at the start of
each working period

Using the manual straight edge you find what kind of spot to place the rolling
straightedge? - ANSWER Locate a flat area with the manual straightedge and place the
rolling straightedge next to the manual straightedge and the gauge should read 0

The 3/16 and the 3/8 shims go under which wheels during calibration - ANSWER The
outside wheels to measure the low and the center to measure the high. Gauge should
read 3/16 on the 3/16 shim and vice versa for the 3/8 shims. Make sure the center
wheel moves up and down freely.

Calibration materials for Straightedge - ANSWER Rolling Straightedge
Manual Straightedge
Manual Measurement (ruler)
x4 3/16 shims 5mm thick
x4 3/8 shims 10mm thick

When to perform final straightedge - ANSWER After an entire lane has been paved

When to perform final straightedge - ANSWER Pavement should be an ambient
temperature

You cannot use the straightedge until it has been properly - ANSWER calibrated

When performing the straightedge procedure - ANSWER Maintain proper traffic
management and safety

Cross slopes can be either done - ANSWER Manually or with a smart level

When using a manual cross slope you first - ANSWER Place a simple level on
pavement

After placing the simple level on the pavement then you - ANSWER Raise the down
end of the level until it is level (bubble center)

, After the simple level is lifted until it is level you measure what - ANSWER The length
of the simple level and the height between the (previously down) end of the level to the
pavement

Formula to calculate the manual cross slope - ANSWER Calculate the slope using the
formula

( h / l ) x 100 = slope %

Requirements for the rolling Straightedge - ANSWER Must have a read out gauge, kept
clean and in working order, low and high reading, and marks to the nearest 1/16 (1mm)

Rolling Straightedge pulled at - ANSWER 3 to 5mph or less

Deficiencies pointed out with rolling straightedge you should first - ANSWER Mark the
pavement at the center wheel where the needle initially shows a deficiency and where is
ends. Also record location and measurements of deficiency.

Core sampling is used for - ANSWER testing density
and permeability

Core sampling equipment - ANSWER Concrete saw
Diamond bit core drill
Size of core depends on test
Ice chest (Optional)
Ice (Optional)
Asphalt to patch hole

During core sampling the barrel should always be - ANSWER perpendicular to
pavement

Core sampling patching - ANSWER Fill hole with patch mix, if in lifts tamp each lift

Storing cores - ANSWER Store in ice chest with bagged ice on top or put in an air
conditioned cab
Best stored upright in a cool place
DO NOT THROW INTO PICKUP

Determine Bulk Specific gravity on sampled cores - ANSWER Trim to correct lift
Weigh dry sample if dry otherwise
Place in water (77+-2) for 4+-1 minute
Then roll within five seconds to achieve SSD weight
Then dry to a constant weight with fan or core dryer

Bulk Specific Gravity formula - ANSWER dry / SSD - water weight = BSG

Document information

Uploaded on
August 31, 2024
Number of pages
6
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$9.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
TheExamMaestro
3.6
(18)
Sold
160
Followers
5
Items
3820
Last sold
1 day ago




Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions