CEA PLTW Test Questions and Answers (100% Pass)
CEA Practice Part A - Answer✔️✔️-*See CEA Practice Part A Answer Key
for Short Response*
1. Choose the phrase that best completes the following sentence: "A civil
engineer is responsible for ________________."
A. the aesthetic quality of a structure.
B. the patterns of traffic flow into and out of a structure.
C. the way a project relates to the surrounding environment.
D. the design of the foundation and the soil bearing capacity. - Answer✔️✔️-
B. the patterns of traffic flow into and out of a structure.
2. A municipality is planning the construction of a new water treatment
facility. Who would be responsible for the design of the system to treat the
water?
A. Contractor
B. Architect
C. Civil Engineer
D. Regulator - Answer✔️✔️-C. Civil Engineer
3. Which of the following would NOT be included as part of a civil
engineer's project documentation?
A. Plot plan
1
, ©SOPHIABENNET@2024/2025 Monday, August 19, 2024 10:32 PM
B. Window types
C. Site sketches
D. Soil testing - Answer✔️✔️-B. Window types
4. A floor plan is a sectional view of a floor as seen from what height above
the finished floor level?
A. 2 feet
B. 4 feet
C. 6 feet
D. ceiling height - Answer✔️✔️-B. 4 feet
5. A set of plans from which a structure will be built that includes floor
plans, elevations and building sections to graphically convey the design
solution is known as______________________.
A. presentation drawings.
B. working drawings.
C. isometric drawings.
D. thumbnail sketches. - Answer✔️✔️-B. working drawings.
6. A drawing that shows the measured area of land and depicts the layout
of the property.
A. Floor Plan
B. Parcel Boundary
2