©PREP4EXAMS@2024 [REAL-EXAM-DUMPS] Wednesday, July 31, 2024 9:10 AM
ARE 366 Exam 2 Practice Questions and Answers (100% Pass)
Contract Modification - ✔️✔️Modification of existing contract clause or detail
Contract change - ✔️✔️Differing contract inclusion that has not yet been accepted by one
or both parties
Canons of contract interpretation - ✔️✔️1. Handwritten is more powerful than print
2. Specific is more powerful than general
3. -----------------------------------------
Spearin Doctrine - Favors Contractors - ✔️✔️1. Contractor should worry about following
instructions, bot analyzing drawings/specs
2. Contractors are not liable for design defects if all plans/specs are followed exactly as
recieved
Spearin Doctrine - Favors Owners - ✔️✔️1. -------------------------------------
2. ------------------------------------
Progress payments are based upon: - ✔️✔️1. -----------------------------------
2. Quality Checks
3. Contractual Requirements & what was agreed upon in contract
1
, ©PREP4EXAMS@2024 [REAL-EXAM-DUMPS] Wednesday, July 31, 2024 9:10 AM
Legal Defense Claims in court - ✔️✔️1. ----------------------------
2. ---------------------------
3. ---------------------------
Basic principles regarding design work and responsibility - ✔️✔️1. The contractor must
follow drawings and specs as outlined by A/E
2. Must communicate with A/E on any design clarification issues
Why do government contracts include a differing site conditions clause? - ✔️✔️1.
Geotech reports can be wrong
2. Site conditions are not entirely known
3. --------------------------------
To prove Constructive Acceleration, a contractor must prove: - ✔️✔️1. Acceleration
caused productivity loss
2. There was a delay not comitted by contractor
3. Notice requirements were followed
4. There was negotiation, mediation, and attempt to prevent acceleration
5. Show time extension was requested
6. Request was denied
Advantages of Dispute Review Boards - ✔️✔️1. Less costly than court
2
ARE 366 Exam 2 Practice Questions and Answers (100% Pass)
Contract Modification - ✔️✔️Modification of existing contract clause or detail
Contract change - ✔️✔️Differing contract inclusion that has not yet been accepted by one
or both parties
Canons of contract interpretation - ✔️✔️1. Handwritten is more powerful than print
2. Specific is more powerful than general
3. -----------------------------------------
Spearin Doctrine - Favors Contractors - ✔️✔️1. Contractor should worry about following
instructions, bot analyzing drawings/specs
2. Contractors are not liable for design defects if all plans/specs are followed exactly as
recieved
Spearin Doctrine - Favors Owners - ✔️✔️1. -------------------------------------
2. ------------------------------------
Progress payments are based upon: - ✔️✔️1. -----------------------------------
2. Quality Checks
3. Contractual Requirements & what was agreed upon in contract
1
, ©PREP4EXAMS@2024 [REAL-EXAM-DUMPS] Wednesday, July 31, 2024 9:10 AM
Legal Defense Claims in court - ✔️✔️1. ----------------------------
2. ---------------------------
3. ---------------------------
Basic principles regarding design work and responsibility - ✔️✔️1. The contractor must
follow drawings and specs as outlined by A/E
2. Must communicate with A/E on any design clarification issues
Why do government contracts include a differing site conditions clause? - ✔️✔️1.
Geotech reports can be wrong
2. Site conditions are not entirely known
3. --------------------------------
To prove Constructive Acceleration, a contractor must prove: - ✔️✔️1. Acceleration
caused productivity loss
2. There was a delay not comitted by contractor
3. Notice requirements were followed
4. There was negotiation, mediation, and attempt to prevent acceleration
5. Show time extension was requested
6. Request was denied
Advantages of Dispute Review Boards - ✔️✔️1. Less costly than court
2