The code official - Answer- When requirements necessary for proper operation of a proposed mechanical system are not specifically covered by the code, such requirements shall be determined by____________________.
State the reason for disapproval in writing to the applicant - Answer- Where the code
official finds that a proposed alternative material does not comply with the intent of the code provisions, the code official shall _________________.
Interpret - Answer- The code official has the authority to______________the provisions of the code.
At the job site - Answer- One set of construction documents shall be kept_______________until completion of the project.
Holder of the permit - Answer- The______________shall be responsible for the scheduling of inspections.
Ground source heat pump loop systems - Answer- Which of the following installations is permitted to be backfilled prior to an underground inspection?
Code official - Answer- Mechanical systems shall be tested, with such test made by the permit holder and observed by the________________.
10 - Answer- A permit is not required for a self-contained refrigeration system that contains a maximum of_______________pound(s) of refrigerant.
International energy conservation code - Answer- Heating, Ventilating and air-
conditioning systems shall be designed and installed for efficient use of energy in accordance with the________________.
Manufacturer's - Answer- Appliances that are part of the building mechanical system shall not be converted to a different fuel, except where approved and in accordance with the_______________instructions.
2 - Answer- Bored holes for the installation of piping shall be located at least______________Inch(es) From the top and bottom of the solid wood joist.
33 1/3 - Answer- A bored hole in the floor joist is limited in diameter to__________Percent of the depth of the joist.
1/6 - Answer- Notches in the top or bottom of solid wood joists are limited to_______________of the depth of the joists.
1/3 - Answer- Notches in the top or bottom of solid wood joists shall not be located in
the middle______________of the span.
40 - Answer- Studs used in non-bearing partitions are permitted to be cut or notched to a maximum depth of______________percent of the stud depth.
60 - Answer- For studs in a non-bearing partition, the maximum permitted diameter of a bored hole is______________Percent of the depth of the stud.
5/8 - Answer- Bored holes shall not be near than______________inch to the edge of
the stud.
Be listed for installation in the closet - Answer- A boiler installed in the closet must__________________.
18 - Answer- When located within a repair garage, appliances with an ignition source
shall be elevated such that the ignition source is a minimum of________________inches above the garage floor.
Oil fired boiler in the storage closet - Answer- The installation of a(n) ______________is prohibited.