Your installation is refurbishing an existing PES facility built in 1968. Do you need to complete an ESSP? - Correct Answer- Yes, and it requires DDESB approval. As distance from the potential explosion site decreases, the potential for damage to an exposed site from an explosion.... - Correct Answer- increases. Your installation is increasing the NEW for a storage site built in 1969 and storing a hazard division that was not previously approved for that location. Do you need to complete an ESSP? - Correct Answer- Yes, and it requires DDESB approval. Intraline distance (ILD) is the minimum distance permitted between... - Correct Answertwo operating buildings. The purpose of an ESSP is to ensure safety, provide specifications, and... - Correct Answer- establish limits. You must submit an ESSP for DDESB approval if the installation is... - Correct Answerbuilding an ES within an existing ESQD arc. Failing to submit a successful ESSP may result in... - Correct Answer- reduced operational capacity. Which are the phases of the ESSP process in order? - Correct Answer- Development and Evaluation, Submission, DDESB Review, and Implementation. The Expedited Approval Request must... - Correct Answer- explain why an expedited approval is required. Which part of the ESSP package contains background information, site location, and the reason for the ESSP submission? - Correct Answer- ESSP narrative Which ESSP category addresses facilities and operations that do not completely conform to deterministic QD criteria or meet the risk-based criteria in DESR 6055.09 Edition 1? - Correct Answer- HSP Which is NOT a common mistake when submitting an ESSP? - Correct AnswerSending the ESSP to USATCES
Document information
- Uploaded on
- September 25, 2023
- Number of pages
- 2
- Written in
- 2023/2024
- Type
- Exam (elaborations)
- Contains
- Questions & answers