LEED Green Associate Exam Practice Questions With Answers | Latest Update 2023/2024 | 100% Verified
For existing buildings, project teams carry out some important responsibilities. For existing buildings, which plan that the project teams must complete? A. A CFC PHASE-OUT PLAN B. WORK DISTRIBUTION PLAN C. SITE SELECTION D. DESIGNING PLAN LEED GA Prep Exam Questions and Answers (Verified Answers) Latest Update 2023 E. FULFILL THE REQUIREMENTS - correct answers A. A CFC PHASE-OUT PLAN Building analyzing software tools take inputs and determine the energy behavior of a building¡¯s systems over time. What is another feature of the software weather data that can be input into the software? A. AVAILABILITY OF REAL-TIME B. MAXIMUM TIME C. AVAILABILITY OF CONSECUTIVE TIME D. MINIMUM TIME E. AVAILABILITY OF IDLE TIME - correct answers A. AVAILABILITY OF REALTIME Which are the reasons of underperforming the building systems? - correct answers Building systems can underperform for several reasons: (1)The building was not properly configured, (2)The design did not account for all sources of building efficiency, (3)The building is not properly maintained, (4)The use of the building has changed over time. LEED GA Prep Exam Questions and Answers (Verified Answers) Latest Update 2023 According to the measurement and verification protocol what would be required for determination of energy savings? A. ACCURATE MEASUREMENT B. PROPER INVESTIGATION C. ACCURATE VERIFICATION D. PROPER MAINTENANCE E. REPLICABLE METHODOLOGY - correct answers A.&E. The determination of energy savings requires both accurate measurement and replicable methodology, known as a measurement and verification protocol. Commissioning is the process of verifying the building¡¯s energy related systems are installed, calibrated, and perform according to the project requirements. What is commissioning in all the LEED rating systems? A. A NON PROVISION B. A NON PRECAUTION C. A PRECAUTION D. A PRECONSCIOUS LEED GA Prep Exam Questions and Answers (Verified Answers) Latest Update 2023 E. A PREREQUISITE - correct answers E. Commissioning is a prerequisite in all the LEED rating systems. Hydrocarbons (HC) are used as natural refrigerants. Which could you say hydrocarbons that are used as natural refrigerants? (Choose 3) A. PROPANE B. ETHANE C. AMMONIA 氨 D. CARBON DIOXIDE E. ISO-PENTANE - correct answers A, B & E HC, Hydrocarbons, such propane丙烷, butane丁烷, ethane乙烷, isobutene异丁烯, and iso-pentane异戊烷. IEQ ensures excellent indoor air quality and comfort. What is reduced by it? A. TOXINS B. AIR ELEMENTS LEED GA Prep Exam Questions and Answers (Verified Answers) Latest Update 2023 C. DUST D. VIRUSES - correct answers A. Indoor Environmental Quality: Ensure Excellent Indoor Air Quality (IEQ) and Comfort,Reduce Toxins & Pollutants. Whole-building design, as previously mentioned in this study, is the ideal way to work with LEED credits what is created? A. STRATEGIES B. SYNERGIES 协同效应 C. DESIGN PROCESS D. SELECTING SITE - correct answers Whole-building design, as previously mentioned in this study, is the ideal way to work with LEED credits to create synergies. What step would take to control equitably total global emissions of substances that deplete it, with the ultimate objective of their elimination on the basis of developments in scientific knowledge? A. BY TAKING PREVIOUSLY PROTECTIONS LEED GA Prep Exam Questions and Answers (Verified Answers) Latest Update 2023 B. BY TAKING PRECAUTIONARY ACTIONS C. BY TAKING PREVIOUSLY TRIALS D. BY TAKING PRECAUTIONARY MEASURES E. BY TAKING PREVIOUSLY DETERMINATIONS - correct answers D. Determined to protect the ozone layer by taking precautionary measures to control equitably total global emissions of substances that deplete it, with the ultimate objective of their elimination on the basis of developments in scientific knowledge. 33 The project team must make sure the building is functioning as intended based on the design. Which are the other functions of project team that need to be make sure? (Choose 2) For existing buildings, project teams carry out some important responsibilities. For existing buildings, which plan that the project teams must complete? A. A CFC PHASE-OUT PLAN B. WORK DISTRIBUTION PLAN C. SITE SELECTION D. DESIGNING PLAN LEED GA Prep Exam Questions and Answers (Verified Answers) Latest Update 2023 E. FULFILL THE REQUIREMENTS - correct answers A. A CFC PHASE-OUT PLAN Building analyzing software tools take inputs and determine the energy behavior of a building¡¯s systems over time. What is another feature of the software weather data that can be input into the software? A. AVAILABILITY OF REAL-TIME B. MAXIMUM TIME C. AVAILABILITY OF CONSECUTIVE TIME D. MINIMUM TIME E. AVAILABILITY OF IDLE TIME - correct answers A. AVAILABILITY OF REALTIME Which are the reasons of underperforming the building systems? - correct answers Building systems can underperform for several reasons: (1)The building was not properly configured, (2)The design did not account for all sources of building efficiency, (3)The building is not properly maintained, (4)The use of the building has changed over time. LEED GA Prep Exam Questions and Answers (Verified Answers) Latest Update 2023 According to the measurement and verification protocol what would be required for determination of energy savings? A. ACCURATE MEASUREMENT B. PROPER INVESTIGATION C. ACCURATE VERIFICATION D. PROPER MAINTENANCE E. REPLICABLE METHODOLOGY - correct answers A.&E. The determination of energy savings requires both accurate measurement and replicable methodology, known as a measurement and verification protocol. Commissioning is the process of verifying the building¡¯s energy related systems are installed, calibrated, and perform according to the project requirements. What is commissioning in all the LEED rating systems? A. A NON PROVISION B. A NON PRECAUTION C. A PRECAUTION D. A PRECONSCIOUS LEED GA Prep Exam Questions and Answers (Verified Answers) Latest Update 2023 E. A PREREQUISITE - correct answers E. Commissioning is a prerequisite in all the LEED rating systems. Hydrocarbons (HC) are used as natural refrigerants. Which could you say hydrocarbons that are used as natural refrigerants? (Choose 3) A. PROPANE B. ETHANE C. AMMONIA 氨 D. CARBON DIOXIDE E. ISO-PENTANE - correct answers A, B & E HC, Hydrocarbons, such propane丙烷, butane丁烷, ethane乙烷, isobutene异丁烯, and iso-pentane异戊烷. IEQ ensures excellent indoor air quality and comfort. What is reduced by it? A. TOXINS B. AIR ELEMENTS LEED GA Prep Exam Questions and Answers (Verified Answers) Latest Update 2023 C. DUST D. VIRUSES - correct answers A. Indoor Environmental Quality: Ensure Excellent Indoor Air Quality (IEQ) and Comfort,Reduce Toxins & Pollutants. Whole-building design, as previously mentioned in this study, is the ideal way to work with LEED credits what is created? A. STRATEGIES B. SYNERGIES 协同效应 C. DESIGN PROCESS D. SELECTING SITE - correct answers Whole-building design, as previously mentioned in this study, is the ideal way to work with LEED credits to create synergies. What step would take to control equitably total global emissions of substances that deplete it, with the ultimate objective of their elimination on the basis of developments in scientific knowledge? A. BY TAKING PREVIOUSLY PROTECTIONS LEED GA Prep Exam Questions and Answers (Verified Answers) Latest Update 2023 B. BY TAKING PRECAUTIONARY ACTIONS C. BY TAKING PREVIOUSLY TRIALS D. BY TAKING PRECAUTIONARY MEASURES E. BY TAKING PREVIOUSLY DETERMINATIONS - correct answers D. Determined to protect the ozone layer by taking precautionary measures to control equitably total global emissions of substances that deplete it, with the ultimate objective of their elimination on the basis of developments in scientific knowledge. 33 The project team must make sure the building is functioning as intended based on the design. Which are the other functions of project team that need to be make sure? (Choose 2)
Document information
- Uploaded on
- August 8, 2023
- Number of pages
- 13
- Written in
- 2023/2024
- Type
- Exam (elaborations)
- Contains
- Questions & answers