GOVT 404 FINAL TEST 2023
Quiz of 29 pages for the course GOVT 404 at Liberty University (GOVT 404
FINAL TEST)
GOVT 404 Final Test
• Quiz 1
0 out of 5 points
TripleCyl contracts with ManuPow Partners to sell 100
forklift engines at a cost of $2,000each. TripleCyl agrees to
deliver the engines in one installment on April 1. On March
20, TripleCyl delivers 98 engines together with a note
stating that the remaining two engines would be delivered
the following day. The next day TripleCyl delivers two
engines. Is ManuPow Partners entitled to reject the
engines? Choose the best answer:
Selected Solution
No, TripleCyl has substantially performed, and substantial
performanceis not breach.
• Quiz 2
Mandie interviews Carlton for a new job at Mandie’s company. At
the end of the
5 out of 5 points
interview, Mandie offers to hire Carlton on a two-year
,contract with a salary of $42,000, plus health insurance.
Carlton asks if he can “sleep on it” and let Mandie know
his answer the next day. Mandie agrees. That night,
Mandie texts Carlton the message: “I just found someone
, else for the position, but thanks for interviewing and best
of luck.” Choose the best answer:
Selected Solution
Carlton cannot accept the offer because it was
revoked.
• Quiz 3
5 out of 5 points
GC Company is a building contractor, performing work for
the Owner of a construction project. The contract between
GC Company and Owner provides that there will be six
phases of work. Further it provides that at the end of each
phase of work, GC Company should submit its request for
payment to Owner’s architect. Once the architect approves
the work performed, GC Company is entitled to payment of
1/6 of the total contract price. GC Company performs work
on phases 1, 2, 3, 4, and 5, and the Owner pays for the
work despite the fact that GC Company never submitted its
requests for payment to the architect and never got the
architect’s approval of the work. When GC Company
submits its request for the sixth and final payment, the
Owner refuses to pay it on the grounds that GC Company
has never submitted it, or any other request for payment,
to the architect. What is GC Company’s most likely
argument that it is entitled to payment?
Selected Solution