100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
Another Trojan Horse- Case Project Management Case Studies in Project, Program, and Organizational Project Management, ISBN: 9781118174296 $5.48   Add to cart

Case

Another Trojan Horse- Case Project Management Case Studies in Project, Program, and Organizational Project Management, ISBN: 9781118174296

 20 views  0 purchase
  • Course
  • Institution
  • Book

This note includes my personal answer to cases in the book mentioned below: Milosevic, D. Z., Patanakul, P., & Srivannaboon, S. (2010). Case Studies in Project, Program, and Organizational Project Management. John Wiley and Sons Inc.

Preview 1 out of 3  pages

  • February 13, 2022
  • 3
  • 2017/2018
  • Case
  • Dr. manahan
  • A
avatar-seller
CASE STUDIES IN PROJECT MANAGEMENT SYSTEMS 1



Another Trojan Horse
Stevan Jovanovic

I. PROBLEM & SOLUTION
Problem: One of the biggest challenges for this company was the change in mindset from an
operating company to a project management company. The transition from an operating company
to a project management company could result in difficulty when a person has spent their entire
career focusing on project execution. The tendency for that type of person might be to revert to
old ways.
Solution: They looked for the latest project management techniques and undergone four - day
training regarding Scope Management, Cost Management, Time Management, and Risk
Management to be equipped upon the execution of the plan.

II. EXECUTIVE SUMMARY

John Lackey received an award for Best Project Management of Utility Plant in the United States
in 2000 since the Trojan Nuclear Plant, was formally shut down in 1996. To begin with, when it
comes to shutting down a nuclear plant, removing it, and placing it in an area for safety in the
future, it was easier said than done. However, it needs to be at least relocated since the plant was
near a city that could cause harm to the people living within and near the area. The nuclear plant
was named Trojan and was considered the largest and most powerful nuclear plant of its day and
it would need to undergo decommissioning since it was an essential part of the plant lifecycle.
Thus, it would require a carefully planned project whereas every tiny detail must be calculated,
studied, and revised to increase the percentage of success of the project before it could be executed.
There was no room for errors in this project due to its potential harm, thus, the project would be
examined not only by the authorities but by the general public as well. John and his company have
undergone a four-day training course to ensure that they are equipped to complete the project. To
start with the decommissioning of the plant, the project was broken down into smaller projects so
that they could apply their newly acquired skills in project management. One of the projects was
the elimination of the central reactor which includes relocating the entire reactor hundreds of miles
from the plant location. It was the first attempt and would be the biggest and most complicated
whereas the safest way to eradicate the reactor was in one piece carefully without damaging any
part of the reactor. Fortunately, they succeeded in safely lifting the reactor and placing it at its final
destination. They managed every detail of the move and the move was a success. Thus, the team
and the company had made their spot on the pages of project management history.

III. BRIEF HISTORY

John Lackey received an award for Best Project Management of Utility Plant in the United
States in 2000 since the Trojan Nuclear Plant, was formally shut down in 1996. To begin with,
when it comes to shutting down a nuclear plant, removing it, and placing it in an area for safety in
the future, it was easier said than done. However, it needs to be at least relocated since the plant
was near a city that could cause harm to the people living within and near the area. The nuclear
plant was named Trojan and was considered the largest and most powerful nuclear plant of its day
and was located on a huge site that sustained lots of equipment. However, it still needs to undergo

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller GelC. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $5.48. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

73314 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$5.48
  • (0)
  Add to cart