,Question 1. An assignment names the following competencies: Undertaking
preliminary stakeholder analysis and context evaluation; Defining and verifying initial
project scope parameters; Conducting delivery options analysis; Operating change
control processes for managing scope changes and variations. Which additional
competency would expand the named scope rather than repeat one of its existing
parts?
A. Operating change control processes for managing scope changes and variations
B. Defining and verifying initial project scope parameters
C. Assessing project success against original baseline objectives and business cases
D. Undertaking preliminary stakeholder analysis and context evaluation
Correct Answer: C
Full Explanation:
Assessing project success against original baseline objectives and business cases is the additional
competency. Its focus is Assessing project success against original baseline objectives and
business cases. Each other choice is already included in the assignment, so selecting it repeats
part of the existing scope rather than adding a different competency.
Question 2. The planned review covers Establishing strategic alignment with
organizational objectives and governance frameworks; Project Handover and
Transition; Conducting project post-implementation reviews and performance
evaluations. Evidence has been assembled for Establishing strategic alignment with
organizational objectives and governance frameworks; Project Handover and
Transition. Which additional evidence addresses the remaining competency?
A. Evidence addressing Estimating activity durations and resource requirements
B. Evidence addressing Conducting project post-implementation reviews and performance
evaluations
C. Evidence addressing Managing final deliverables acceptance and operational transition
D. Evidence addressing Executing quality assurance and quality control measures
Correct Answer: B
Full Explanation:
The unaddressed competency is Conducting project post-implementation reviews and
performance evaluations. Relevant evidence must address Conducting project
post-implementation reviews and performance evaluations. Evidence about an already covered
activity or a different competency cannot demonstrate that the remaining work has been
completed.
Record 17840 2
,Question 3. An assignment names the following competencies: Defining and verifying
initial project scope parameters; Schedule Development and Management; Developing
the Risk Management Plan; Identifying, analyzing, and prioritizing project risks and
establishing initial response strategies. Which additional competency would expand
the named scope rather than repeat one of its existing parts?
A. Developing the Risk Management Plan
B. Identifying, analyzing, and prioritizing project risks and establishing initial response strategies
C. Archiving project documentation, capturing lessons learned, and releasing project resources
D. Schedule Development and Management
Correct Answer: C
Full Explanation:
Archiving project documentation, capturing lessons learned, and releasing project resources is
the additional competency. Its focus is Archiving project documentation. Each other choice is
already included in the assignment, so selecting it repeats part of the existing scope rather than
adding a different competency.
Question 4. A work allocation is intended to cover Defining overarching project
objectives, success criteria, and high-level deliverables; Cost and Financial Planning;
Managing ongoing stakeholder expectations and communication flows, but the listed
activities are Defining overarching project objectives; Managing ongoing stakeholder
expectations and communication flows; Progress Reporting and Stakeholder
Communication. Which single replacement aligns the allocation with its intended
scope?
A. Replace Progress Reporting and Stakeholder Communication with Establishing initial project
boundaries and constraints
B. Replace Progress Reporting and Stakeholder Communication with Cost and Financial Planning
C. Replace Progress Reporting and Stakeholder Communication with Scope Definition and
Verification
D. Replace Progress Reporting and Stakeholder Communication with Developing and securing
approval for the Project Charter or Brief
Correct Answer: B
Full Explanation:
The allocation is missing Cost and Financial Planning, whose relevant activity is Cost and Financial
Planning. The substituted activity, Progress Reporting and Stakeholder Communication, belongs
to a different competency. Replacing that substitution restores the missing part while retaining
the other required activities.
Record 17840 3
, Question 5. A work allocation is intended to cover Conducting project
post-implementation reviews and performance evaluations; Archiving project
documentation, capturing lessons learned, and releasing project resources, but the
listed activities are Archiving project documentation; Schedule Development and
Management. Which single replacement aligns the allocation with its intended scope?
A. Replace Schedule Development and Management with Monitoring and controlling project
execution against baseline plans (scope, schedule, budget)
B. Replace Schedule Development and Management with Conducting project
post-implementation reviews and performance evaluations
C. Replace Schedule Development and Management with Developing the Risk Management Plan
D. Replace Schedule Development and Management with Operating change control processes for
managing scope changes and variations
Correct Answer: B
Full Explanation:
The allocation is missing Conducting project post-implementation reviews and performance
evaluations, whose relevant activity is Conducting project post-implementation reviews and
performance evaluations. The substituted activity, Schedule Development and Management,
belongs to a different competency. Replacing that substitution restores the missing part while
retaining the other required activities.
Question 6. A work allocation is intended to cover Formulating Resource Management
and Team Management Plans; Communications and Information Management;
Planning project communications and establishing a Communications Register;
Finalizing procurement activities, contractor evaluations, and contract closeouts;
Conducting project post-implementation reviews and performance evaluations, but
the listed activities are Formulating Resource Management and Team Management
Plans; Communications and Information Management; Finalizing procurement
activities; Conducting project post-implementation reviews and performance
evaluations; Administrative and Financial Closure. Which single replacement aligns
the allocation with its intended scope?
A. Replace Administrative and Financial Closure with Managing project human resources and
evaluating team performance
B. Replace Administrative and Financial Closure with Developing Information Management Plans
for data security
C. Replace Administrative and Financial Closure with Planning project communications and
establishing a Communications Register
D. Replace Administrative and Financial Closure with Risk Management Planning
Correct Answer: C
Full Explanation:
The allocation is missing Planning project communications and establishing a Communications
Register, whose relevant activity is Planning project communications and establishing a
Communications Register. The substituted activity, Administrative and Financial Closure, belongs
to a different competency. Replacing that substitution restores the missing part while retaining
the other required activities.