[General PM] Nature of Project - correct answersTemporary, creative unique outputs, and drive changes [General PM] Project Charter - correct answersAuthorizes the PM, sets stakeholder expectations, and prevents constant changes [General PM] Charter signatory - correct answersSigned by the sponsor or senior management with funding authority [General PM] Project management plan - correct answersIncludes plans and baselines [General PM] Planning lifecycles - correct answersPlan for the project lifecycle (phases) and development lifecycle (e.g., waterfall, agile) [General PM] Project phases - correct answers(each phase starts with the initiating process, including reviewing and updating the project charter); initiating - planning - executing - controlling - closing [General PM] Multiple sponsors - correct answersincreases communication needs and time in Configuration Management due to competing needs [General PM] Management strategy - correct answersA carefully developed overall approach to leading an organization; if the team needs constant pushing to get things done, there is no strategy [General PM] Reporting structure - correct answersDifferent reporting lines in various organizational structures (e.g., matrix, functional, projectized) [General PM] Type of PMO: Controlling - correct answersMandates compliance [General PM] Type of PMO: Supportive - correct answersProvides templates and best practices [General PM] Type of PMO: Directive - correct answersHigh degree of ove

Content preview

CAPM RISK MANAGEMENT & PROJECT CONTROL EXAM PREP
[General PM] Nature of Project - correct answersTemporary, creative unique outputs, and drive changes

[General PM] Project Charter - correct answersAuthorizes the PM, sets stakeholder expectations, and
prevents constant changes

[General PM] Charter signatory - correct answersSigned by the sponsor or senior management with
funding authority

[General PM] Project management plan - correct answersIncludes plans and baselines

[General PM] Planning lifecycles - correct answersPlan for the project lifecycle (phases) and
development lifecycle (e.g., waterfall, agile)

[General PM] Project phases - correct answers(each phase starts with the initiating process, including
reviewing and updating the project charter); initiating - planning - executing - controlling - closing

[General PM] Multiple sponsors - correct answersincreases communication needs and time in
Configuration Management due to competing needs

[General PM] Management strategy - correct answersA carefully developed overall approach to leading
an organization; if the team needs constant pushing to get things done, there is no strategy

[General PM] Reporting structure - correct answersDifferent reporting lines in various organizational
structures (e.g., matrix, functional, projectized)

[General PM] Type of PMO: Controlling - correct answersMandates compliance

[General PM] Type of PMO: Supportive - correct answersProvides templates and best practices

[General PM] Type of PMO: Directive - correct answersHigh degree of oversight

[Scope Management] Scope baseline - correct answersDeveloped by project team with stakeholder
input

[Scope Management] Precise scope statement - correct answersMust be detailed and accurate

[Scope Management] Constraints - correct answersListed in the scope statement, assumptions log, or
constraints log

[Scope Management] Scope reviews - correct answersPreliminary and final reviews

[Scope Management] Customer approval - correct answersApproved product scope, not project scope

, [Scope Management] Quality control vs scope validation - correct answersQuality control for
correctness, validate scope for acceptance

[Scope Management] Scope changes - correct answersExplained to the customer for informed decisions

[Scope Management] WBS Development - correct answersWork Breakdown Structure - created by the
team, used for stakeholder communication

[Scope Management] WBS benefits - correct answersEnsures team buy-in, prevents scope issues, key
tool to manage scope

[Scope Management] Context diagram - correct answersVisual tool for collecting requirements

[Scope Management] Code of accounts - correct answersUnique WBS IDs

[Scope Management] Control Accounts - correct answersHigher-level than planning and work packages,
defined in scheduling

[Scope Management] Estimating cost issues - correct answersDue to lack of scope definition

[Scope Management] Validate scope - correct answersDone in monitoring and controlling phase
(technical acceptance)

[Scope Management] Scope statement parts - correct answersDescription, deliverables,
assumptions/constraints, acceptance criteria, exclusions

[Schedule Management] Estimate activity durations - correct answersUse WBS and RBS at detailed
levels

[Schedule Management] Activity attributes - correct answersinclude task details (who, where,
predecessor/successor links, duration, float) but not costs

[Schedule Management] Milestones - correct answersSet in a project charter and defined during activity
planning; have zero duration

[Schedule Management] Precedence diagramming method (PDM) - correct answersMaps out tasks in
order for execution

[Schedule Management] What if analysis - correct answersUses Monte Carlo analysis to calculate
possible durations of the overall project

[Schedule Management] Total Float - correct answersCalculated as LS - ES

[Schedule Management] Rolling wave planning - correct answersDetailed planning for imminent tasks,
high-level planning for future tasks

[Schedule Management] Brooks' law - correct answersAdding people late can delay the project

Document information

Uploaded on
October 21, 2026
Number of pages
12
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$7.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Sold
0
Followers
0
Items
176
Last sold
-




Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions