WGU CQN1 TASK 1
FREQUENTLY TESTED ACTUAL EXAM QUESTIONS
WITH CORRECT ANSWERS
Question 1.
Plan Communications Management, Outputs
ANSWER
Communications management plan
Project management plan updates
Project documents updates
Question 2.
Monitor Risks, Inputs
ANSWER
Project management plan, project documents, work performance data, work performance
reports
Question 3.
Estimate Activity Resources, Outputs
ANSWER
Resource requirements, Basis of estimates, Resource breakdown structure, Project document
updates
Question 4.
Develop Team, Tools & Techniques
ANSWER
Colocation, Virtual teams, Communication technology, Interpersonal and team skills,
Recognition and rewards, Training, Individual and team assessments, Meetings
,Question 5.
Identify Risks, Inputs
ANSWER
Project Management Plan, Project documents, Agreements, Procurement documentation,
EEFs, OPAs
Question 6.
Monitor Risks, Tools & Techniques
ANSWER
Data analysis, audits, and meetings
Question 7.
Estimate Activity Resources, Tools & Techniques
ANSWER
Expert judgement, Bottom-up estimating, Analogous estimating, Parametric estimating, Data
analysis, Project management information system, Meetings
Question 8.
Manage Communications, Outputs
ANSWER
Project communications, Project Management Plan updates, Project document updates, OPA
updates
Question 9.
Estimate Costs, Outputs
ANSWER
Cost estimates, Basis of estimates, Project document updates
, Question 10.
Define Activities, Inputs
ANSWER
Project Management Plan, EEFs, OPAs
Question 11.
Plan Stakeholder Engagement, Tools & Techniques
ANSWER
Expert judgement, Data gathering, Data analysis, Decision making, Data representation,
Meetings
Question 12.
Sequence Activities, Inputs
ANSWER
Project Management Plan, Project documents, EEFs, OPAs
Question 13.
Plan Risk Responses, Outputs (rr)
ANSWER
Change requests, project management plan updates, project documents updates (rr)
Question 14.
Acquire Resources, Outputs
ANSWER
Physical resource assignments, Project team assignments, Resource calendars, Change
requests, Project Management Plan updates, Project document updates, EEF updates, OPA
updates
FREQUENTLY TESTED ACTUAL EXAM QUESTIONS
WITH CORRECT ANSWERS
Question 1.
Plan Communications Management, Outputs
ANSWER
Communications management plan
Project management plan updates
Project documents updates
Question 2.
Monitor Risks, Inputs
ANSWER
Project management plan, project documents, work performance data, work performance
reports
Question 3.
Estimate Activity Resources, Outputs
ANSWER
Resource requirements, Basis of estimates, Resource breakdown structure, Project document
updates
Question 4.
Develop Team, Tools & Techniques
ANSWER
Colocation, Virtual teams, Communication technology, Interpersonal and team skills,
Recognition and rewards, Training, Individual and team assessments, Meetings
,Question 5.
Identify Risks, Inputs
ANSWER
Project Management Plan, Project documents, Agreements, Procurement documentation,
EEFs, OPAs
Question 6.
Monitor Risks, Tools & Techniques
ANSWER
Data analysis, audits, and meetings
Question 7.
Estimate Activity Resources, Tools & Techniques
ANSWER
Expert judgement, Bottom-up estimating, Analogous estimating, Parametric estimating, Data
analysis, Project management information system, Meetings
Question 8.
Manage Communications, Outputs
ANSWER
Project communications, Project Management Plan updates, Project document updates, OPA
updates
Question 9.
Estimate Costs, Outputs
ANSWER
Cost estimates, Basis of estimates, Project document updates
, Question 10.
Define Activities, Inputs
ANSWER
Project Management Plan, EEFs, OPAs
Question 11.
Plan Stakeholder Engagement, Tools & Techniques
ANSWER
Expert judgement, Data gathering, Data analysis, Decision making, Data representation,
Meetings
Question 12.
Sequence Activities, Inputs
ANSWER
Project Management Plan, Project documents, EEFs, OPAs
Question 13.
Plan Risk Responses, Outputs (rr)
ANSWER
Change requests, project management plan updates, project documents updates (rr)
Question 14.
Acquire Resources, Outputs
ANSWER
Physical resource assignments, Project team assignments, Resource calendars, Change
requests, Project Management Plan updates, Project document updates, EEF updates, OPA
updates