1. Under the DBIA Design-Build Done Right® framework, which project delivery attribute most
fundamentally distinguishes design-build from design-bid-build?
A) The owner retains full control over the final design details.
B) A single contract entity assumes responsibility for both design and construction.
C) The lowest responsive bidder is always awarded the contract.
D) Construction cannot begin until the design is 100% complete.
Correct Answer: B) A single contract entity assumes responsibility for both design and
construction.
EXPERT RATIONALE: Design-build consolidates design and construction under one contract, creating
a single point of responsibility. This contrasts with design-bid-build, where the owner contracts
separately with a designer and a builder. The other options describe characteristics of traditional
delivery, not design-build.
2. An owner is preparing a Request for Qualifications (RFQ) for a design-build project. According to
DBIA best practices, which evaluation approach is most appropriate?
A) Weighting price at 90% and qualifications at 10%.
B) Focusing heavily on the qualifications of the design-builder and key team members.
C) Selecting the firm with the lowest overhead and profit percentage.
D) Requiring full design submittals from all interested firms at the RFQ stage.
Correct Answer: B) Focusing heavily on the qualifications of the design-builder and key team
members.
EXPERT RATIONALE: DBIA Best Practices emphasize that design-build procurement should focus
significantly on qualifications and demonstrated integration history. Price-heavy or low-overhead
selection undermines the collaborative model. Full design submittals at RFQ are inefficient and
contrary to phased procurement.
3. During a best-value design-build procurement, when should the owner open and evaluate price
proposals relative to technical proposals?
A) Simultaneously with technical proposals to ensure transparency.
B) Before technical evaluation to establish a budget ceiling.
C) After technical proposals have been evaluated and scored.
D) Only after contract award to validate the winning team's pricing.
Correct Answer: C) After technical proposals have been evaluated and scored.
EXPERT RATIONALE: DBIA best practices support evaluating technical proposals first, then opening
price, to prevent price from biasing technical judgment. This sequenced approach preserves the
integrity of qualifications-based selection. Opening price simultaneously or first can compromise best-
value decision-making.
4. Which of the following best describes the DBIA-recommended approach to risk allocation in
design-build contracts?
A) The owner should retain all design risk to maintain control.
B) Risks should be allocated to the party best equipped to manage and minimize them.
C) The design-builder should accept all risks regardless of controllability.
,D) Risk allocation should be deferred until construction begins.
Correct Answer: B) Risks should be allocated to the party best equipped to manage and minimize
them.
EXPERT RATIONALE: DBIA's standard contract documents reflect a balanced risk allocation
philosophy. Each risk is assigned to the party most capable of managing it, promoting best practices
and reducing disputes. Blanket risk transfer or owner retention of all design risk contradicts this
principle.
5. An owner wants to encourage innovation in a design-build RFP. Which requirements approach
best supports this goal?
A) Prescriptive specifications detailing every material and method.
B) Performance-based requirements describing outcomes and success criteria.
C) A requirement that the design-builder use the owner's preferred design firm.
D) Mandating a specific construction sequence in the RFP.
Correct Answer: B) Performance-based requirements describing outcomes and success criteria.
EXPERT RATIONALE: DBIA Best Practices recommend maximizing performance-based requirements
and minimizing prescriptive ones. Performance requirements give the design-build team flexibility to
propose innovative solutions. Prescriptive specifications and mandated means and methods restrict
innovation.
6. Under a typical DBIA standard form of agreement, what is the design-builder's standard of care
for design professional services?
A) The highest standard attainable in the industry.
B) The care and skill ordinarily used by members of the applicable profession under similar
conditions.
C) A guarantee that the design will be error-free.
D) The owner's subjective satisfaction standard.
Correct Answer: B) The care and skill ordinarily used by members of the applicable profession
under similar conditions.
EXPERT RATIONALE: DBIA contract documents establish the professional standard of care: the skill
and care ordinarily used by practitioners under similar circumstances. This is not a warranty of
perfection or an elevated standard. The standard is consistent with professional licensing norms.
7. What is the primary purpose of conducting confidential meetings with shortlisted design-build
proposers before final proposal submission?
A) To negotiate the final contract price with each team.
B) To allow open and candid exchange of concepts and concerns to improve proposals.
C) To disclose competitors' pricing strategies to all teams.
D) To eliminate the need for a formal technical proposal.
Correct Answer: B) To allow open and candid exchange of concepts and concerns to improve
proposals.
EXPERT RATIONALE: DBIA Best Practices endorse confidential (proprietary) meetings to encourage
dialogue and curtail wasted effort on unacceptable proposals. These meetings are not for price
negotiation or disclosing competitors' information. They improve proposal quality and alignment.
8. In Progressive Design-Build (PDB), how does the owner typically select the design-build team?
A) Primarily on lowest price with a fully developed scope.
B) Primarily on qualifications, with scope and price developed collaboratively after award.
C) By bidding a complete set of prescriptive drawings and specifications.
D) Through a traditional design-bid-build low-bid process.
, Correct Answer: B) Primarily on qualifications, with scope and price developed collaboratively after
award.
EXPERT RATIONALE: Progressive Design-Build emphasizes qualifications-based selection, followed by
collaborative development of scope, design, and price. This differs from traditional best-value design-
build, where price is typically proposed before award. PDB suits projects with conceptual or evolving
requirements.
9. Which document does DBIA recommend owners provide at the RFQ stage to inform proposers
of contract terms?
A) The final executed contract only.
B) A draft design-build contract.
C) The winning team's proposal from a previous project.
D) No contract information until after selection.
Correct Answer: B) A draft design-build contract.
EXPERT RATIONALE: DBIA Best Practices recommend disclosing a draft contract at the RFQ phase so
proposers understand terms and conditions before pursuing the opportunity. This allows teams to
structure their approach and suggest modifications. Withholding contract information until later
increases uncertainty and risk.
10. What does DBIA consider an appropriate use of stipends in design-build procurement?
A) To pay the owner's staff for proposal evaluation.
B) To compensate shortlisted proposers for significant technical work.
C) To guarantee a profit to the winning team.
D) To reduce the contract price after award.
Correct Answer: B) To compensate shortlisted proposers for significant technical work.
EXPERT RATIONALE: Stipends are used to offset the cost of developing substantial technical
proposals, particularly in two-phase procurements. They encourage qualified teams to participate
without bearing unreasonable proposal costs. Stipends are not profit guarantees or evaluation
salaries.
11. Under DBIA's recommended dispute resolution ladder, what typically follows negotiation if the
parties cannot resolve a dispute?
A) Immediate litigation in court.
B) Mandatory, non-binding mediation.
C) Termination of the contract.
D) Arbitration without mediation.
Correct Answer: B) Mandatory, non-binding mediation.
EXPERT RATIONALE: DBIA contract documents provide for negotiation, then mediation, then binding
arbitration (unless the parties elect court). This graduated approach encourages resolution at the
lowest practical level. Litigation is typically a last resort, not the immediate next step.
12. What is the design-builder's obligation regarding continued performance during a dispute
under DBIA standard terms?
A) The design-builder may suspend all work until the dispute is resolved.
B) Both parties must continue performing their duties unless the contract provides otherwise.
C) Only the owner must continue performing.
D) Work stops automatically when a dispute is filed.
Correct Answer: B) Both parties must continue performing their duties unless the contract
provides otherwise.
EXPERT RATIONALE: DBIA General Conditions require continued performance pending dispute