GUIDING PRINCIPLES (Q1–Q8)
Q1. What is the primary purpose of the Design-Build Institute of America (DBIA)?
A) Provide construction insurance
B) Define, teach, and promote best practices in design-build project delivery
C) Regulate construction licensing
D) Sell construction software
Answer: B — DBIA is the leading authority that defines, teaches, and promotes design-
build best practices.
Q2. In which year was DBIA established?
A) 1993
B) 1995
C) 1998
D) 2000
Answer: A — DBIA was established in 1993 .
Q3. What does "Design-Build Done Right" emphasize?
A) Lowest price selection only
B) Best practices in procurement, contracting, and execution
C) Separating design and construction responsibilities
D) Eliminating owner involvement
Answer: B — The core philosophy emphasizes best practices across all three phases .
Q4. Which of the following is a key characteristic of design-build delivery?
A) Separate contracts for design and construction
B) Single point of responsibility for both design and construction
C) Sequential design and construction phases
D) Owner manages multiple contracts
Answer: B — Single point of responsibility is the defining characteristic .
Q5. What does DBIA consider the foundation of successful design-build?
A) Lowest first cost
B) Trust, transparency, and clear roles
C) Maximum risk transfer to the design-builder
D) Minimal owner involvement
,Answer: B — The DBIA mindset emphasizes trust, transparency, clear roles, and fair risk
allocation .
Q6. How many DBIA Best Practices are there?
A) 5
B) 7
C) 10
D) 15
Answer: C — There are 10 Best Practices organized into three categories .
Q7. The DBIA Best Practices are organized into which three categories?
A) Planning, Design, Construction
B) Procurement, Contracting, Execution
C) Quality, Cost, Schedule
D) Pre-award, Award, Post-award
Answer: B — Procurement, Contracting, and Execution .
Q8. What is the purpose of the DBIA Code of Professional Conduct?
A) Increase profits
B) Create an ethical environment where issues can be raised early
C) Reduce project costs
D) Eliminate competition
Answer: B — Ethics and professionalism create an environment for early issue resolution .
FOUNDATIONS OF DESIGN-BUILD DONE RIGHT (Q9–Q16)
Q9. What is the historical foundation of design-build?
A) Design-Bid-Build
B) The Master Builder model
C) Construction Management at Risk
D) Multiple Prime contracts
Answer: B — The Master Builder was responsible for both design and construction .
Q10. Design-build currently represents approximately what percentage of the U.S.
construction market?
A) 33%
B) 47%
C) 58%
D) 72%
Answer: B — Design-build represents approximately 47% of the U.S. construction market .
, Q11. What is the primary advantage of design-build over Design-Bid-Build?
A) Multiple points of responsibility
B) Single point of responsibility and schedule compression through fast-tracking
C) Lower initial design fees
D) Complete separation of liability
Answer: B — Single point of accountability and fast-tracking are key advantages .
Q12. What is "fast-tracking" in design-build?
A) Speeding up construction after design is complete
B) Overlapping design and construction phases
C) Hiring more workers
D) Reducing quality standards
Answer: B — Fast-tracking allows construction to begin before design is fully complete .
Q13. Which delivery method has a rigid separation of design and construction
responsibilities?
A) Design-Build
B) Design-Bid-Build
C) Progressive Design-Build
D) Integrated Project Delivery
Answer: B — Design-Bid-Build separates design and construction .
Q14. What is a key benefit of early collaboration in design-build?
A) Increased disputes
B) Enhanced innovation and constructability input
C) Slower schedule
D) Higher costs
Answer: B — Early collaboration enables innovation and constructability review .
Q15. In larger design-build projects, which party is typically the primarily responsible entity?
A) The Architect
B) The Contractor
C) The Engineer
D) The Owner
Answer: B — The contractor typically leads in larger design-build projects .
Q16. How does design-build differ from Integrated Project Delivery (IPD)?
A) IPD uses a single contract; design-build uses multiple
B) Design-build typically uses a single contract between owner and design-builder; IPD uses
a multi-party agreement
C) They are identical
D) IPD is only for public projects
Answer: B — Design-build = single contract; IPD = multi-party agreement .
answers— 100 Original Items
GUIDING PRINCIPLES (Q1–Q8)
Q1. What is the primary purpose of the Design-Build Institute of America (DBIA)?
A) Provide construction insurance
B) Define, teach, and promote best practices in design-build project delivery
C) Regulate construction licensing
D) Sell construction software
Answer: B — DBIA is the leading authority that defines, teaches, and promotes design-
build best practices.
Q2. In which year was DBIA established?
A) 1993
B) 1995
C) 1998
D) 2000
Answer: A — DBIA was established in 1993 .
Q3. What does "Design-Build Done Right" emphasize?
A) Lowest price selection only
B) Best practices in procurement, contracting, and execution
C) Separating design and construction responsibilities
D) Eliminating owner involvement
Answer: B — The core philosophy emphasizes best practices across all three phases .
Q4. Which of the following is a key characteristic of design-build delivery?
A) Separate contracts for design and construction
B) Single point of responsibility for both design and construction
C) Sequential design and construction phases
D) Owner manages multiple contracts
Answer: B — Single point of responsibility is the defining characteristic .
Q5. What does DBIA consider the foundation of successful design-build?
A) Lowest first cost
B) Trust, transparency, and clear roles
C) Maximum risk transfer to the design-builder
D) Minimal owner involvement
,Answer: B — The DBIA mindset emphasizes trust, transparency, clear roles, and fair risk
allocation .
Q6. How many DBIA Best Practices are there?
A) 5
B) 7
C) 10
D) 15
Answer: C — There are 10 Best Practices organized into three categories .
Q7. The DBIA Best Practices are organized into which three categories?
A) Planning, Design, Construction
B) Procurement, Contracting, Execution
C) Quality, Cost, Schedule
D) Pre-award, Award, Post-award
Answer: B — Procurement, Contracting, and Execution .
Q8. What is the purpose of the DBIA Code of Professional Conduct?
A) Increase profits
B) Create an ethical environment where issues can be raised early
C) Reduce project costs
D) Eliminate competition
Answer: B — Ethics and professionalism create an environment for early issue resolution .
FOUNDATIONS OF DESIGN-BUILD DONE RIGHT (Q9–Q16)
Q9. What is the historical foundation of design-build?
A) Design-Bid-Build
B) The Master Builder model
C) Construction Management at Risk
D) Multiple Prime contracts
Answer: B — The Master Builder was responsible for both design and construction .
Q10. Design-build currently represents approximately what percentage of the U.S.
construction market?
A) 33%
B) 47%
C) 58%
D) 72%
Answer: B — Design-build represents approximately 47% of the U.S. construction market .
, Q11. What is the primary advantage of design-build over Design-Bid-Build?
A) Multiple points of responsibility
B) Single point of responsibility and schedule compression through fast-tracking
C) Lower initial design fees
D) Complete separation of liability
Answer: B — Single point of accountability and fast-tracking are key advantages .
Q12. What is "fast-tracking" in design-build?
A) Speeding up construction after design is complete
B) Overlapping design and construction phases
C) Hiring more workers
D) Reducing quality standards
Answer: B — Fast-tracking allows construction to begin before design is fully complete .
Q13. Which delivery method has a rigid separation of design and construction
responsibilities?
A) Design-Build
B) Design-Bid-Build
C) Progressive Design-Build
D) Integrated Project Delivery
Answer: B — Design-Bid-Build separates design and construction .
Q14. What is a key benefit of early collaboration in design-build?
A) Increased disputes
B) Enhanced innovation and constructability input
C) Slower schedule
D) Higher costs
Answer: B — Early collaboration enables innovation and constructability review .
Q15. In larger design-build projects, which party is typically the primarily responsible entity?
A) The Architect
B) The Contractor
C) The Engineer
D) The Owner
Answer: B — The contractor typically leads in larger design-build projects .
Q16. How does design-build differ from Integrated Project Delivery (IPD)?
A) IPD uses a single contract; design-build uses multiple
B) Design-build typically uses a single contract between owner and design-builder; IPD uses
a multi-party agreement
C) They are identical
D) IPD is only for public projects
Answer: B — Design-build = single contract; IPD = multi-party agreement .