• Wrong document? Swap it for free
  • Written by students who passed
  • Immediately available after payment
  • Read online or as PDF
Sell
Where do you study
Your language
Document preview thumbnail
Preview 4 out of 35 pages
Exam (elaborations)

C215 Operations Management Study Guide (2026/2027) | WGU Exam Review & Assessment Prep

Document preview thumbnail
Preview 4 out of 35 pages

C215 Operations Management Study Guide (2026/2027) | WGU Exam Review & Assessment PrepC215 Operations Management Study Guide (2026/2027) designed for Western Governors University students preparing for the C215 assessment. It reviews key exam-relevant concepts including total quality management, statistical quality control, capacity planning, facility location, product and process design, facility layout, work system design, and JIT/lean systems. C215 STUDY GUIDE WHAT YOU WILL GET A focused C215 study guide with summarized concepts, review material, and major operations management topics for assessment preparation. PLEASE NOTE This is a study and revision resource intended to support exam preparation and reinforce course concepts. C215 Study, Operations Management, WGU C215, WGU Study, Exam Review, Assessment Prep, Operations Study, Management Study, Quality Management, Lean Systems C215 Operations Management Study Guide 2026/2027, WGU C215 Operations Management Study Guide, C215 WGU Exam Review 2026/2027, WGU Operations Management Exam Prep, C215 Operations Management Assessment Prep, C215 Study Guide WGU, Operations Management WGU Study Notes, WGU C215 Study Notes, C215 Operations Management Exam Review, C215 Assessment Study Guide, WGU C215 Assessment Prep, Operations Management Exam Study Guide, C215 Total Quality Management Study Guide, C215 Statistical Quality Control Review, C215 Capacity Planning Study Guide, C215 Facility Location Exam Review, C215 Product Design Study Notes, C215 Facility Layout Study Guide, C215 JIT Lean Systems Review, Western Governors University C215 Study Guide Read less

Content preview

Question 1

,A manufacturing firm notices that small fluctuations in retail customer demand cause
increasingly massive swings in inventory levels and production schedules for its raw
material suppliers upstream. What supply chain phenomenon is occurring?

• A. The Pareto Effect
• B. The Bullwhip Effect
• C. Kanban Desynchronization
• D. Diseconomies of Scale

Correct Answer: B. The Bullwhip Effect

Rationale: The Bullwhip Effect describes how minor variations in retail demand ripple
upstream, causing amplified demand distortion across supply chain tiers.

Question 2

An operation manager wants to evaluate a process using discrete attribute data by
counting the total number of physical scratches on individual refrigerator doors. Which
Statistical Process Control (SPC) chart is most appropriate?

• A. 𝑋̅-chart
• B. 𝑅-chart
• C. 𝑐-chart
• D. 𝑝-chart

Correct Answer: C. 𝑐-chart

Rationale: A 𝑐-chart measures the number of defects per unit (discrete count data). A
𝑝-chart measures the proportion/percentage of defective units.

Question 3

An annual product demand (𝐷) is 10,000 units, ordering cost (𝑆) is $50 per order, and
annual holding cost (𝐻) is $4 per unit per year. What is the Economic Order Quantity
(𝑄 ∗ )?

• A. 354 units
• B. 500 units
• C. 250 units
• D. 1,000 units

Correct Answer: B. 500 units

Rationale:

, 2 × 10,000 × 50 1,000,000
𝑄∗ = √ =√ = √250,000 = 500 units
4 4
Question 4

A medical clinic trains its triage staff to double-check patient ID bands using barcode
scanners to ensure medications are never misadministered. Which Lean concept is
being applied?

• A. Poka-Yoke
• B. Heijunka
• C. Kanban
• D. Kaizen

Correct Answer: A. Poka-Yoke

Rationale: Poka-yoke refers to error-proofing techniques that prevent mistakes or make
them immediately obvious.

Question 5

A facility has a design capacity of 200 units per hour and an effective capacity of 160
units per hour. If actual output is 120 units per hour, what is the facility's efficiency?

• A. 60%
• B. 75%
• C. 80%
• D. 125%

Correct Answer: B. 75%

Rationale:

Actual Output 120
Efficiency = = = 0.75 = 75%
Effective Capacity 160
(Note: Utilization would be 120/200 = 60%).

Question 6

During project network scheduling, Activity G has an Early Start Time (𝐸𝑆𝑇) of Day 6, an
Early Finish Time (𝐸𝐹𝑇) of Day 10, a Late Start Time (𝐿𝑆𝑇) of Day 9, and a Late Finish
Time (𝐿𝐹𝑇) of Day 13. What is the total slack time for Activity G?

• A. 0 days
• B. 3 days

, • C. 4 days
• D. 7 days

Correct Answer: B. 3 days

Rationale: Slack = 𝐿𝑆𝑇 − 𝐸𝑆𝑇 = 9 − 6 = 3 days (or 𝐿𝐹𝑇 − 𝐸𝐹𝑇 = 13 − 10 = 3 days).

Question 7

Which quality cost category includes conducting supplier evaluations, preventive
maintenance on production machinery, and staff quality training?

• A. Internal Failure Costs
• B. External Failure Costs
• C. Appraisal Costs
• D. Prevention Costs

Correct Answer: D. Prevention Costs

Rationale: Prevention costs are proactively invested in product design and operational
processes to stop defects before they occur.

Question 8

In a project network diagram, what defines the Critical Path?

• A. The sequence of tasks with the highest total financial cost
• B. The shortest path through the network diagram
• C. The longest path through the network diagram, which dictates minimum
project completion time
• D. The series of non-dependent tasks that can be performed simultaneously

Correct Answer: C. The longest path through the network diagram, which dictates
minimum project completion time

Rationale: The critical path is the longest sequence of dependent activities, having zero
slack time and determining the overall project duration.

Question 9

A company produces high-volume, highly standardized electronic components on a
continuous assembly sequence. Which manufacturing layout strategy is most
appropriate?

• A. Process-Oriented Layout
• B. Fixed-Position Layout

Document information

Uploaded on
October 17, 2026
Number of pages
35
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$17.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Sold
36
Followers
3
Items
2656
Last sold
2 days ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions