Contractor (Class A) Examination with
Practice Questions A
1. A Class A contractor's bid includes a 5% contingency. Mid-project, the owner
directs a change adding 12% to the original scope. Under California law, which action
best preserves the contractor's right to additional compensation and time?
A. Proceed with the change and submit a detailed change order request within 14 days,
documenting cost and time impact.
B. Stop work immediately until a written change order is signed, invoking the owner's
breach.
C. Absorb the change within the contingency and request an extension only if delays
exceed 30 days.
D. File a stop payment notice before performing any changed work to secure payment.
Answer: A. Proceed with the change and submit a detailed change order request
within 14 days, documenting cost and time impact.
Rationale: California law requires timely written notice and documentation of change
orders to preserve rights; proceeding while submitting a change order request within the
contractual notice period is standard. Stopping work (B) may be a breach unless the
contract allows; absorbing the change (C) waives compensation; filing a stop payment
notice (D) is premature and not for change orders.
Page 1 of 90
,2. For a proposed 30-ft cut in a cohesionless sand deposit with a groundwater table at
10 ft depth, which shoring system is most appropriate under Cal/OSHA and
geotechnical best practice?
A. Soil nailing with shotcrete facing
B. Soldier piles and lagging with dewatering
C. Trench shield with hydraulic jacks
D. Sloping to 1.5H:1V with no shoring
Answer: B. Soldier piles and lagging with dewatering
Rationale: Cohesionless sand with high groundwater requires a system that can handle
flowing ground and water; soldier piles with lagging and dewatering are standard. Soil
nailing (A) is unsuitable in clean sand without cohesion; trench shields (C) are for
trenches, not 30-ft cuts; sloping (D) alone is unsafe with groundwater and depth.
Page 2 of 90
,3. A contractor's estimate uses a 20% overhead and profit markup on direct costs. If
direct costs are $1,200,000 and the contractor wins the bid at $1,500,000, what is the
actual gross profit margin?
A. 20.0%
B. 25.0%
C. 16.7%
D. 12.5%
Answer: C. 16.7%
Rationale: Gross profit = $1,500,000 - $1,200,000 = $300,000. Margin = $300,000 /
$1,500,000 = 20%? Wait, 300/1500 = 0.20 = 20%. Actually 300k/1.5M=20%. But if
markup is 20% on cost, bid would be $1.44M; winning at $1.5M yields higher margin.
Compute: profit=300k, revenue=1.5M, margin=20%. So correct is A? Let's recalc:
$1,200,000 * 1.20 = $1,440,000. Winning at $1,500,000 gives profit $300,000, margin
300/1500=20%. So answer A. But option A is 20.0%. I mistakenly set correct C. Correct is
A. Explanation: Gross profit = $1,500,000 - $1,200,000 = $300,000. Gross profit margin =
$300,000 / $1,500,000 = 20.0%. Markup on cost would be 25%, but margin is 20%.
Distractors: 25% is markup, 16.7% is profit/revenue if profit=250k, 12.5% is 150k/1.2M.
4. Under California Civil Code § 8170, a design professional's lien on a private work is
limited to the lesser of the reasonable value of services or the amount agreed. If a
geotechnical engineer provided $80,000 in services but the contract was for $60,000,
what is the maximum lien amount?
A. $80,000
B. $60,000
C. $70,000
D. $0
Answer: B. $60,000
Rationale: Civil Code § 8170 limits the design professional's lien to the lesser of the
reasonable value of services or the amount agreed. Since the contract amount ($60,000) is
less than the reasonable value ($80,000), the lien is capped at $60,000. Options A and C
exceed the contract; D is incorrect because a valid lien right exists.
Page 3 of 90
, 5. A SWPPP for a 15-acre grading project must include which of the following to
comply with the California Construction General Permit?
A. A certified erosion control plan by a licensed landscape architect
B. A rain event action plan (REAP) and post-rain event inspections
C. Continuous turbidity monitoring at all discharge points
D. A minimum 50-ft vegetated buffer around all disturbed areas
Answer: B. A rain event action plan (REAP) and post-rain event inspections
Rationale: The Construction General Permit requires a Rain Event Action Plan (REAP)
and post-rain event inspections for Risk Level 2 or 3 sites. Option A is not mandatory; C is
only required for certain risk levels or TMDL; D is a best management practice but not
universally mandated.
6. In a public works project subject to California prevailing wage law, which method
correctly calculates the required overtime rate for a worker classified as a laborer
(Group 1) working 10 hours on a holiday?
A. 1.5 times the basic hourly rate for all hours over 8 in a day.
B. 2 times the basic hourly rate for all hours over 8 in a day.
C. 1.5 times the basic rate for the first 8 hours and 2 times for hours over 8.
D. 2 times the basic rate for all hours worked on a holiday.
Answer: B. 2 times the basic hourly rate for all hours over 8 in a day.
Rationale: Under California Labor Code and prevailing wage determinations, all hours
worked over 8 in a day on a public works project are paid at double the basic rate (not 1.5)
for laborers. Option A is the federal standard; C is incorrect because the first 8 are straight
time; D is incorrect because holiday premium applies only to hours over 8, not all hours.