Phase I equipment is related to all of the following except: - Answer Dispenser mounted vapor
recovery equipment
According to EO VR-201/202-N, the only authorized hose configuration is: - Answer Any hose
Configuration
The most current ARB approved Phase II vapor recovery is: - Answer EVR
When a certified Healy Technician is replacing the VP 1000 during operational hours, they
should do all of the following to elongate potentials problems except: - Answer Review service
with gas station operator
The following component is not part of the Healy Phase II vapor recovery system: - Answer
Healy Model 900 Vapor Motor
The max dispensing flow rate of a Healy 900 Series EVR nozzle is: - Answer 10 GPM
According to VR-201/202-N, a ________ should be installed on the Healy system if the flow rate
is above 10 GPM - Answer Flow limiter
The Quarterly Inspection and Testing of a Healy Phase II EVR system should include the
following except: - Answer Conduct a pressure decay test by a Healy Certified Technician
The first sign of oxygen depletion is: - Answer Accelerated breathing and heartbeat
According to PEI 500, each of the following are proper methods of removing a portion of a GDF
from service except: - Answer Noting event in the defective equipment log
What procedure checks the integrity of the vapor check valve in the nozzle? - Answer Nozzle
bag test
Which of the following conditions is a Healy certified technician not required to repair? -
Answer Reconnection of a breakaway after a drive off
, What procedure is required after a nozzle spout change? - Answer Nozzle automatic shutoff
test
A vapor recovery system generally uses what unit of measurement? - Answer Inches of water
column
During the annual inspection and testing of the vapor recovery system; the first three steps are
to:
1. Conduct static pressure performance of the Healy Clean Air Separator
2. Conduct pressure decay test
3. Conduct dispenser vapor line tightness test
What is the 4th step? - Answer Conduct V/L test on all nozzles
What is the lower limit of acceptable V/L for a nozzle? - Answer .95
In order for a technician to be authorized to clear an ISD Alarm, he or she must be certified by
which of the following? - Answer Manufacture
The clean Air Separator belongs to which system? - Answer Healy phase II
All of the following items should be on hand to react to a spill except: - Answer Class A fire
extinguisher
Which is not a component of a Healy phase-II vapor recovery system? - Answer Universal 37
Which of the following is not a part of hanging hardware? - Answer Husky Model 4885
What is mounted on the top of the manifold vent mast? - Answer Pressure/vacuum vent cap
Connecting a copper wire from the tank to the earth constitutes what? - Answer Grounding
What is the maximum allowable fuel flow from the dispenser? - Answer 10 GPM
What is the maximum length of the hose/breakaway/swivel when measured to the base of the
nozzle? - Answer 20 feet