New Hampshire Septic Installer Exam 2 – System Installation & Construction Exam 300 Actual Questions And Correct Answers With Rationale Latest Update Already Graded A+ Assured Pass

Document preview thumbnail
Preview 4 out of 88 pages

Pass the New Hampshire Septic Installer Exam Part 2 with this comprehensive 2025 updated study guide featuring 300 actual multiple-choice questions, correct answers, and detailed rationales. Covering RSA 485-A and Env-Wq 1000 regulations, permits and administration, setbacks and minimum distances, septic tank construction and sizing, distribution systems and piping, effluent disposal areas and leaching fields, installation procedures, pumps, alarms and controls, inspections, troubleshooting, plan reading, contours, field layout, safety, and maintenance, this resource mirrors the official NHDES exam and helps installers, designers, and septic professionals master every regulatory and technical requirement. Perfect for certification, recertification, and building the knowledge needed to pass with confidence.

Content preview

NEW HAMPSHIRE SEPTIC INSTALLER EXAM 2 –
SYSTEM INSTALLATION & CONSTRUCTION EXAM
300 ACTUAL QUESTIONS AND CORRECT ANSWERS
WITH RATIONALE LATEST UPDATE ALREADY
GRADED A+ ASSURED PASS




Section 1: Regulations, Permits & Administration (Questions 1–
30)
1. Under which New Hampshire statute does NHDES issue individual sewage
disposal system (ISDS) installer permits?
A. RSA 485-A:35
B. RSA 485-A:29
C. RSA 483-B
D. RSA 482-A

Answer: A
Rationale: RSA 485-A:35 specifically governs the issuance of installer permits for
subsurface sewage disposal systems. RSA 485-A:29 establishes the overall
authority for water pollution and waste disposal regulations.

2. What is the minimum passing score required on each part of the NH Septic
Installer exam?
A. 70%
B. 75%
C. 80%
D. 85%

Answer: C
Rationale: NHDES requires a minimum score of 80% on both Part 1 and Part 2.
Scores are not averaged, so a high score on one part cannot compensate for a
failing score on the other.

,3. Beginning in Spring 2026, how are the two parts of the NH Septic Installer exam
administered?
A. On the same day
B. On separate days
C. Part 2 is taken online
D. Part 1 is a field test

Answer: B
Rationale: Beginning in Spring 2026, Part 1 and Part 2 are administered on
separate days. Applicants must pass Part 1 to be eligible to sit for Part 2.

4. Which NHDES administrative chapter governs subdivisions and individual
sewage disposal system (ISDS) design rules?
A. Env-Wq 1000
B. Env-Wq 402
C. Env-Ws 1000
D. Env-A 1000

Answer: A
Rationale: Chapter Env-Wq 1000 contains the subdivision and individual sewage
disposal system design rules in New Hampshire. This is the primary rule reference
for the installer exam.

5. May a floor drain discharge to an ISDS without separate approval under
applicable groundwater-discharge rules?
A. Yes, in any garage
B. Yes, if the property is residential
C. Yes, if the drain is trapped
D. No

Answer: D
Rationale: Env-Wq 1012.06 states that floor drains shall not be used unless
approved under Env-Wq 402 or a predecessor rule. Floor drains can introduce
contaminants not appropriate for a normal domestic ISDS. Installers should verify
the intended waste stream before connecting such a drain. Rule reference: Env-Wq
1012.06

6. Can a newly constructed ISDS be covered or placed in operation before final
inspection and approval?
A. No

,B. Yes, for up to 30 days
C. Yes, if the installer photographs it
D. Yes, if the owner signs a waiver

Answer: A
Rationale: Env-Wq 1004.06 prohibits covering or placing the constructed system
in operation before final inspection and approval by the department or its
authorized agent. This allows critical components, elevations, and workmanship to
be verified. Rule reference: Env-Wq 1004.06

7. What extension may a permitted designer or installer request when an ISDS is
actively under construction as the construction approval is expiring?
A. Up to 90 days
B. Exactly one year
C. Up to 30 days only
D. No extension is allowed

Answer: A
Rationale: The rule allows an extension of up to 90 days when an ISDS is actively
under construction and the construction approval is expiring, subject to the
required written request. This is not automatic. Rule reference: Env-Wq 1004

8. May state septic requirements be treated as replacing stricter local requirements?
A. Yes, but only for residential systems
B. Only after final inspection
C. Yes; state approval eliminates local requirements
D. No; state requirements are minimums and local requirements can still apply

Answer: D
Rationale: RSA 485-A:32 states that the chapter does not reduce powers of local
authorities and that state requirements are minimum requirements. An installer
may therefore need to satisfy both state and local conditions. Rule reference: RSA
485-A:32

9. How may NHDES test an applicant for a system installer permit?
A. By written examination only
B. By employer recommendation only
C. By field inspection only
D. By oral examination, written examination, or both

, Answer: D
Rationale: The statute authorizes NHDES to require an oral examination, a written
examination, or both. This gives the department flexibility to test both rule
knowledge and practical understanding. Rule reference: RSA 485-A

10. What is the maximum number of ISDS installations a provisional ITA
generally allows, and for how long?
A. Exactly 100 systems for 2 years
B. Up to 5 systems for 1 year
C. Up to 50 systems over up to 5 years
D. Unlimited systems for 10 years

Answer: C
Rationale: A provisional ITA can allow up to 50 installations over a period of up to
five years while performance testing is conducted. Provisional status is controlled
field evaluation, not unrestricted general use. Rule reference: Env-Wq 1024

11. Which New Hampshire agency has primary authority for regulating subsurface
wastewater disposal systems?
A. NH Department of Transportation (NHDOT)
B. NH Department of Environmental Services (NHDES)
C. NH Department of Health and Human Services (DHHS)
D. NH Office of Planning and Development

Answer: B
Rationale: NHDES, through its Subsurface Systems Bureau, has primary authority
for regulating subsurface wastewater disposal systems under RSA 485-A and
administrative rules Env-Wq 1000.

12. What must an installer do if a general ITA with conditions requires a specific
manufacturer installation manual?
A. Use any older version available
B. Ignore the manual if local practice differs
C. Install as a conventional system without checking conditions
D. Follow the approved manual and all stated conditions

Answer: D
Rationale: A general ITA with conditions may require compliance with a specific
approved design or installation manual. The conditions are part of the technology
authorization. Deviating from them can mean the installed system no longer

Document information

Uploaded on
October 13, 2026
Number of pages
88
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$21.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
PrepPulse
3.8
(9)
Sold
55
Followers
4
Items
1593
Last sold
23 hours ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions