Question 1.
What is an accelerometer used for?
- Temperature measurement
- Acoustic monitoring
- Vibration measurement
- Oil analysis
ANSWER
Vibration measurement
Question 2.
Corrective work is performed following preventive maintenance when __________.
- The schedule calls for it
- The supervisor requests it
- The PM work was performed incorrectly
- Problems are discovered
ANSWER
Problems are discovered
Question 3.
Slips and falls are the worst safety hazards when __________.
- Cleaning fans
- Mopping floors
- Lifting heavy objects
- Driving a tug
ANSWER
Mopping floors
,Question 4.
Supply errors can be caused by relying on __________ without monitoring their performance.
- Customers
- Employees
- Suppliers
- Inspectors
ANSWER
Suppliers
Question 5.
Preventive maintenance is best described as what?
- Periodic in nature
- Exhausting
- Breakdown repair
- Flexible
ANSWER
Periodic in nature
Question 6.
A board with tool outlines for placement is called a __________ and is a good way to make sure tools are
returned to their proper storage space between uses.
- Storyboard
- Shadow board
- Board of tools
- Storage bin
ANSWER
Shadow board
Question 7.
The frequency of maintenance is usually an item found on the __________.
- Preventive maintenance schedule
- Work order
- Warranty card
- Hold card
ANSWER
Preventive maintenance schedule
,Question 8.
A maintenance technician should arrange to have all routine tools and supplies ready to perform
preventive maintenance on a machine in order to __________.
- Increase equipment downtime
- Minimize equipment downtime
- Make sure that the job is done correctly
- Make sure that the machine parts are still available
ANSWER
Minimize equipment downtime
Question 9.
Placing tools and equipment where they can be reached with minimal strain is a characteristic of a
__________.
- Poorly designed workstation
- Well-designed workstation
- Old style workstation
- Pull system
ANSWER
Well-designed workstation
Question 10.
What can be done after a corrective action form is completed?
- The form is saved in a safe and secure place.
- The maintenance technician reviews the work order.
- The supervisor is summoned to determine whether the job is complete.
- Preventive maintenance should be documented as completed.
ANSWER
Preventive maintenance should be documented as completed.
, Question 11.
The first thing an employee should do when discovering a building maintenance issue that negatively
impacts his/her work area is __________.
- Report the situation to the supervisor
- Try to fix the problem
- Go home until the problem is fixed
- Ignore the problem
ANSWER
Report the situation to the supervisor
Question 12.
How often the maintenance will occur is the primary consideration of what type of maintenance?
- Predictive
- Reactive
- Responsive
- Preventive
ANSWER
Preventive
Question 13.
Reactive Maintenance is considered a(n) __________ activity.
- Unplanned maintenance
- Planned maintenance
- Highly responsive maintenance
- Chemical-related maintenance
ANSWER
Unplanned maintenance
Question 14.
In a well-organized plant, it should take a worker __________ to find the right tool.
- 30 seconds
- 1 minute
- 5 minutes
- 10 minutes
ANSWER
30 seconds
WITH VERIFIED ANSWERS
Question 1.
What is an accelerometer used for?
- Temperature measurement
- Acoustic monitoring
- Vibration measurement
- Oil analysis
ANSWER
Vibration measurement
Question 2.
Corrective work is performed following preventive maintenance when __________.
- The schedule calls for it
- The supervisor requests it
- The PM work was performed incorrectly
- Problems are discovered
ANSWER
Problems are discovered
Question 3.
Slips and falls are the worst safety hazards when __________.
- Cleaning fans
- Mopping floors
- Lifting heavy objects
- Driving a tug
ANSWER
Mopping floors
,Question 4.
Supply errors can be caused by relying on __________ without monitoring their performance.
- Customers
- Employees
- Suppliers
- Inspectors
ANSWER
Suppliers
Question 5.
Preventive maintenance is best described as what?
- Periodic in nature
- Exhausting
- Breakdown repair
- Flexible
ANSWER
Periodic in nature
Question 6.
A board with tool outlines for placement is called a __________ and is a good way to make sure tools are
returned to their proper storage space between uses.
- Storyboard
- Shadow board
- Board of tools
- Storage bin
ANSWER
Shadow board
Question 7.
The frequency of maintenance is usually an item found on the __________.
- Preventive maintenance schedule
- Work order
- Warranty card
- Hold card
ANSWER
Preventive maintenance schedule
,Question 8.
A maintenance technician should arrange to have all routine tools and supplies ready to perform
preventive maintenance on a machine in order to __________.
- Increase equipment downtime
- Minimize equipment downtime
- Make sure that the job is done correctly
- Make sure that the machine parts are still available
ANSWER
Minimize equipment downtime
Question 9.
Placing tools and equipment where they can be reached with minimal strain is a characteristic of a
__________.
- Poorly designed workstation
- Well-designed workstation
- Old style workstation
- Pull system
ANSWER
Well-designed workstation
Question 10.
What can be done after a corrective action form is completed?
- The form is saved in a safe and secure place.
- The maintenance technician reviews the work order.
- The supervisor is summoned to determine whether the job is complete.
- Preventive maintenance should be documented as completed.
ANSWER
Preventive maintenance should be documented as completed.
, Question 11.
The first thing an employee should do when discovering a building maintenance issue that negatively
impacts his/her work area is __________.
- Report the situation to the supervisor
- Try to fix the problem
- Go home until the problem is fixed
- Ignore the problem
ANSWER
Report the situation to the supervisor
Question 12.
How often the maintenance will occur is the primary consideration of what type of maintenance?
- Predictive
- Reactive
- Responsive
- Preventive
ANSWER
Preventive
Question 13.
Reactive Maintenance is considered a(n) __________ activity.
- Unplanned maintenance
- Planned maintenance
- Highly responsive maintenance
- Chemical-related maintenance
ANSWER
Unplanned maintenance
Question 14.
In a well-organized plant, it should take a worker __________ to find the right tool.
- 30 seconds
- 1 minute
- 5 minutes
- 10 minutes
ANSWER
30 seconds