• Wrong document? Swap it for free
  • Written by students who passed
  • Immediately available after payment
  • Read online or as PDF
Sell
Where do you study
Your language
Document preview thumbnail
Preview 4 out of 33 pages
Exam (elaborations)

Ladwp Electric Station Operator Study Guide Comprehensive Exam Questions With Correct Answers And Rationales Latest Update| Instant Download

Document preview thumbnail
Preview 4 out of 33 pages

This study guide gives you realistic practice questions for the LADWP Electric Station Operator exam, each with a correct answer and a clear rationale. It covers bus differential relays, transformer protection, safe switching and grounding, SCADA alarms, lockout relays, capacitor banks, breaker failure, and DGA interpretation. Use it to review key concepts and get comfortable with the question format before test day.

Content preview

LADWP Electric Station Operator
Study Guide Comprehensive Exam
Questions with Correct Answers and
Rationales Latest Update 2026 |
LADWP Electric Station Operator Study Guide Comprehensive |
Comprehensive Examination
LADWP Electric Station Operator Study Guide
Comprehensive Exam Questions with Correct Answers and
Rationales Latest Update 2026 actual exam preparation




INTRODUCTION
This document is an important and very helpful preparation
resource for LADWP Electric Station Operator Study Guide
Comprehensive Exam Questions with Correct Answers and
Rationales Latest Update 2026. Every item uses a focused exam
stem, four response options, a keyed response, and a clear
rationale, making it easier to understand the subject, spot
distractors, and build real exam confidence.




Page 1

, Question 1
A 230 kV bus differential relay (87B) operates for a fault on the bus. Which of
the following best explains why the relay must be high-impedance or
percent-differential with harmonic restraint?
A. To prevent maloperation due to CT saturation during through-faults
and to avoid tripping on magnetizing inrush current.
B. To ensure fast operation for internal faults while remaining stable for
external faults and inrush.
C. To provide backup protection for the bus and adjacent lines.
D. To coordinate with the transformer differential relay and avoid
nuisance tripping.
Correct Answer: B - To ensure fast operation for internal faults
while remaining stable for external faults and inrush.


RATIONALE
Bus differential protection must be both dependable for internal faults
and secure against external faults and inrush. Harmonic restraint
blocks during transformer energization, while percent-differential or
high-impedance settings prevent misoperation from CT saturation.
Option A is partially correct but incomplete; B captures the dual
requirement. C and D describe backup and coordination, not the
primary reason for the specific relay design.

Question 2
During a switching sequence to isolate a 115 kV circuit breaker for
maintenance, the operator must apply grounds. Which of the following
correctly describes the sequence according to LADWP safe switching
procedures?
A. Open breaker, open both disconnects, test for absence of voltage,
apply grounds on the line side of the breaker.
B. Open breaker, open both disconnects, test for absence of voltage, apply
grounds on the bus side of the breaker.


Page 2

, C. Open breaker, open both disconnects, apply grounds on both sides of

the breaker without voltage test.

D. Open breaker, open both disconnects, test for absence of voltage,
apply grounds on the breaker terminals.
Correct Answer: A - Open breaker, open both disconnects, test
for absence of voltage, apply grounds on the line side of the
breaker.


RATIONALE
Proper grounding requires testing for absence of voltage after opening
disconnects, then applying grounds on the side where work will be
performed. For breaker maintenance, grounds are typically applied on
the line side to protect against backfeed. Option B places grounds on
the bus side, which may not protect the work area; C omits the voltage
test; D may not provide adequate protection if the breaker is the
isolation point.

Question 3
A transformer is rated 100 MVA, 230/115 kV, with 10% impedance. A
three-phase fault occurs on the 115 kV bus. Assuming infinite bus on the 230
kV side, what is the approximate fault current on the 115 kV side?
A. 2,510 A
B. 5,020 A
C. 10,040 A
D. 1,255 A
Correct Answer: B - 5,020 A


RATIONALE
Base current on 115 kV side = 100 MVA / (3 × 115 kV) 502 A. Fault
current = base current / per-unit impedance = .10 5,020 A.
Options A, C, and D are off by factors of 2, 2, and 0.25 respectively,
likely from misapplication of 3 or MVA base.



Page 3

, Question 4
In a SCADA system, an operator receives a 'Transformer Sudden Pressure'
alarm. Which of the following actions is most appropriate?
A. Immediately trip the transformer manually and investigate.
B. Verify the alarm, check for concurrent alarms (e.g., differential,
overcurrent), and dispatch field personnel to inspect.
C. Acknowledge the alarm and continue monitoring; sudden pressure
alarms are often nuisance.
D. Reduce transformer load to 50% and wait for further indications.
Correct Answer: B - Verify the alarm, check for concurrent
alarms (e.g., differential, overcurrent), and dispatch field
personnel to inspect.


RATIONALE
A sudden pressure alarm may indicate an internal fault. The operator
should verify the alarm, look for corroborating indications (e.g.,
differential relay, oil level, temperature), and dispatch personnel.
Immediate manual trip (A) may be unnecessary if it's a false alarm,
but ignoring (C) is dangerous. Reducing load (D) without
investigation is not standard.

Question 5
Which of the following best describes the purpose of a lockout relay (86
device) in a substation protection scheme?
A. To provide time delay for overcurrent coordination.
B. To automatically reclose the breaker after a transient fault.
C. To trip and lock out the breaker, requiring manual reset after a
protective relay operation.
D. To monitor and display fault current magnitude.
Correct Answer: C - To trip and lock out the breaker, requiring
manual reset after a protective relay operation.


Page 4

Document information

Uploaded on
October 8, 2026
Number of pages
33
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$30.00

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
GoldenExams
4.4
(73)
Sold
58
Followers
17
Items
10385
Last sold
2 days ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions