PJM Generation Dispatcher Sample Exam | UPDATED
Questions with 100% Verified Answers
Q1: Real time transmission constraints or contingencies may be
alleviated with generators operating
A: D. off cost ( out of merit )
Q2: A. below 60 hertz
B. on a new price curve
C. on a new cost curve
D. off cost ( out of merit)
A:
Q3: Monitoring LMP may give insights into
A: A. system constraints
Q4: A. system constraints
B. system voltage
C. system frefuency
D. time error
A:
Q5: PJM calls for which of the following to recover the ACE so that
tie line schedules are maintained ?
A: B. synchronized Reserves
Q6: A. IRC ( instantaneous reserve check )
B. synchronized Reserves
C. supplemential reserves
D. minimun generation calculation
A:
Q7: If not cancelled by PJM , the minimum generation alert expires
A: A. at the end of the specified light load period
Q8: A. at the end of the specified light load period
B. when notified by NERC
C. 12 hours after the alert was issued
D. after a 24 hour period
A:
, Q9: When PJM declares a hot weather alert , the generation
dispatcher should
A: B. 1 and 3 only
1. determine if maintenance can be deferred
Q10: 1. determine if maintenance can be deferred
2. notift transmission operators
3. notify all generating stations and key personnel
4. direct all generating stations to reduce output
A: 3. notify all generating stations and key personnel
Q11: A. 1 and 2 only
B. 1 and 3 only
C. 2 and 4 only
D. 3 and 4 only
A:
Q12: During system restoration, the two categories of reserves are
A: C. dynamic and spinning
Q13: A. dynamic and secondary
B. spinning and quick start
C. dynamic and spinning
D. spinning and primary
A:
Q14: During system restoration, frequency should be maintained
between
A: C. 59.75 and 61.00 hertz
Q15: A. 59.50 and 60.00 hertz
B. 59.75 and 61.50 hertz
C. 59.75 and 61.00 hertz
D. 59.50 and 60.50 hertz
A:
Q16: PJM issues a heave load voltage schedule. Member
companies who own generation facilities should
A: B. ensure voltage regulators on generating units are in service on automatic
Q17: A. remove 230 kV capacitors from service
B. ensure voltage regulators on generating units are in service
Questions with 100% Verified Answers
Q1: Real time transmission constraints or contingencies may be
alleviated with generators operating
A: D. off cost ( out of merit )
Q2: A. below 60 hertz
B. on a new price curve
C. on a new cost curve
D. off cost ( out of merit)
A:
Q3: Monitoring LMP may give insights into
A: A. system constraints
Q4: A. system constraints
B. system voltage
C. system frefuency
D. time error
A:
Q5: PJM calls for which of the following to recover the ACE so that
tie line schedules are maintained ?
A: B. synchronized Reserves
Q6: A. IRC ( instantaneous reserve check )
B. synchronized Reserves
C. supplemential reserves
D. minimun generation calculation
A:
Q7: If not cancelled by PJM , the minimum generation alert expires
A: A. at the end of the specified light load period
Q8: A. at the end of the specified light load period
B. when notified by NERC
C. 12 hours after the alert was issued
D. after a 24 hour period
A:
, Q9: When PJM declares a hot weather alert , the generation
dispatcher should
A: B. 1 and 3 only
1. determine if maintenance can be deferred
Q10: 1. determine if maintenance can be deferred
2. notift transmission operators
3. notify all generating stations and key personnel
4. direct all generating stations to reduce output
A: 3. notify all generating stations and key personnel
Q11: A. 1 and 2 only
B. 1 and 3 only
C. 2 and 4 only
D. 3 and 4 only
A:
Q12: During system restoration, the two categories of reserves are
A: C. dynamic and spinning
Q13: A. dynamic and secondary
B. spinning and quick start
C. dynamic and spinning
D. spinning and primary
A:
Q14: During system restoration, frequency should be maintained
between
A: C. 59.75 and 61.00 hertz
Q15: A. 59.50 and 60.00 hertz
B. 59.75 and 61.50 hertz
C. 59.75 and 61.00 hertz
D. 59.50 and 60.50 hertz
A:
Q16: PJM issues a heave load voltage schedule. Member
companies who own generation facilities should
A: B. ensure voltage regulators on generating units are in service on automatic
Q17: A. remove 230 kV capacitors from service
B. ensure voltage regulators on generating units are in service