CON 200 BUSINESS DECISIONS FOR CONTRACTING
UPDATED ACTUAL QUESTIONS WITH CORRECT
ANSWERS
Question 1.
Although undefinitized contract actions (UCAs) may be necessary to support urgent needs,
these actions are not a desirable form of contracting because the government bears the
majority of the cost and risk during the undefinitized period.

ANSWER
True



Question 2.
How does a cost-plus-incentive-fee (CPIF) contract differ from a fixed-price incentive firm (FPIF)
contract?

ANSWER
CPIF contracts do not have a ceiling price



Question 3.
Which of the following is a factor that must be considered when determining the depth and
breadth of acquisition planning that a requirement will demand?

ANSWER
Urgency of need



Question 4.
A tsunami has slammed into Kunsan Air Base, causing extreme damage to the runway. After
preservation of life and limb, it is critical that Kunsan be able to resume its flying mission. You
have been tasked with getting this runway up and running as soon as possible. How can you
best accomplish this objective?

ANSWER
Award an undefinitized contract action in the form of a letter contract



Question 5.
All of the following factors must be considered when determining the depth and breadth of
acquisition planning required; the complexity of the requirement, acquisition history, dollar size
of need.

ANSWER
True




1

, Question 6.
On a Navy ship construction contract, 50 percent of the award fee money, or $28 million, was
based on management criteria that did not directly relate to shipbuilding requirements. What
does the use of such criteria represent?

ANSWER
-DoD's ability to structure the contract in a way that effectively motivates contractors to improve
performance and achieve acquisition outcomes *-DoD's failure to structure the contract in a way that
effectively motivates contractors to improve performance and achieve acquisition outcomes -DoD's
practice of paying the contractor only when acquisition outcomes are achieved -DoD's use of
objective criteria to measure performance under an incentive contract.



Question 7.
One of the key characteristics that differentiates the various types of incentive contracts is
whether or not objective targets can be established for performance. Which incentive type
contract is most appropriate when objective targets for performance can be established?

ANSWER
-Cost-plus-award-fee *-Cost-plus-incentive-fee -Fixed-price award fee -Firm-fixed price



Question 8.
You are planning a solicitation that offers a government property. Identify the item that you will
require a contractor to submit with his/her offer.

ANSWER
-The specific date during which property will be used *-A description of the Property Management
Plan -A statement that property is furnished as is -A Property Control System



Question 9.
You are working on an undefinitized contract action (UCA) for the purchase of cargo hooks for
the CH-47 (NTE) price is $7,000,000. Can you obligate the total amount at time of award? Why
or why not?

ANSWER
-Yes, the regulations allow you to obligate 100% of the NTE price prior to definitization -No, the
regulations only allow you to obligate up -Yes, the regulations allow you to obligate 20 percent of the
NTE price prior to definitization *-No, the regulations only allow you to obligate up to 50 percent of
the estimated definitized contract cost price prior to definitization



Question 10.
As a best practice, when should the small business professional become involved in acquisition
planning?

ANSWER
As early as possible in the procurement process




2

Document information

Uploaded on
October 5, 2026
Number of pages
12
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$17.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
FocusFile7
4.0
(29)
Sold
299
Followers
4
Items
76015
Last sold
7 hours ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions