NYC DCAS Civil Engineer Exam | Latest Verified Questions and Detailed Answers

Document preview thumbnail
Preview 4 out of 138 pages

OVERVIEW DESCRIPTION: This Comprehensive set of multiple choice questions is designed for the NYC DCAS Civil Engineer Exam, administered by the New York City Department of Citywide Administrative Services (DCAS) through its Bureau of Examinations. The exam structure typically combines an Education and Experience (E&E) evaluation with a written multiple-choice component, and it is designed to determine whether candidates meet the qualifications for placement on an eligible list for civil service appointment in New York City. The content assesses measurable professional experience across core operational domains typical to NYC infrastructure agencies such as the DOT, DEP, and DDC, including project management and field supervision, design and infrastructure review, regulatory compliance and material standards, and contract administration and dispute resolution. Candidates are evaluated on their ability to apply engineering principles to practical scenarios involving municipal contractors, plan specifications, building codes, and public works contracts, reflecting the responsibilities of Civil Engineer positions within city service.

Content preview

1|Page




NYC DCAS Principal Construction Project
Manager Exam | Latest Verified Questions and
Detailed Answers

OVERVIEW DESCRIPTION:
This Comprehensive set of multiple choice questions is designed for the NYC DCAS Principal
Construction Project Manager Exam, a highly competitive civil service examination administered
by the New York City Department of Citywide Administrative Services (DCAS) for high-level
public works management roles across agencies such as DDC, DOB, DOT, and NYCHA. The exam
uses scenario-based, real-life situational questions to assess applied judgment rather than rote
memorization, covering core domains including construction laws and regulations, cost
estimation and budget control, project management fundamentals, safety management and
compliance, contract administration, and project initiation and risk strategies. Candidates are
tested on NYC Construction Codes, zoning and DOB filing processes, labor compliance, cost
analysis and municipal financial reporting, CPM scheduling, stakeholder engagement, OSHA and
local site-safety protocols, incident reporting, hazard mitigation, PPB procurement rules,
contract negotiation and dispute resolution, feasibility studies, site evaluation, risk management,
and quality control systems.


QUESTION 1
A NYC agency is preparing to award a construction contract for a new public library. The
low bidder's price is 22% below the engineer's estimate, and two unit prices are

mathematically unbalanced. Which action is most defensible under the Procurement
Policy Board (PPB) Rules?

A) Reject the bid as non-responsive and award to the next lowest bidder.
B) Award the contract as-is, since the bid is lowest and responsive.

,2|Page


C) Request a written justification from the bidder for the unbalanced unit prices and

evaluate the risk of front-loading before award.
D) Conditionally award the contract, but withhold 10% retention until the unbalanced

items are completed.

CORRECT ANSWER: C


EXPERT RATIONALE: PPB Rules require agencies to evaluate mathematically unbalanced
bids for material unbalancing that could result in the City paying more than the fair

value for the work. Requesting written justification and evaluating the risk of front-
loading is the most defensible action before award.


QUESTION 2
A Principal Construction Project Manager is reviewing a CPM schedule submitted by the

contractor for a major renovation project. The schedule shows the critical path running
through steel erection, but the contractor has assigned a large float to concrete

foundation work. Which statement best describes the primary purpose of CPM in this
context?

A) CPM identifies the longest sequence of activities to establish the minimum project
duration and highlights where float exists.
B) CPM guarantees that the project will finish on time if the contractor follows the
schedule.

C) CPM is primarily used to allocate resources evenly across all activities.
D) CPM eliminates all project risks by identifying the critical path.


CORRECT ANSWER: A

EXPERT RATIONALE: CPM is a network analysis technique that predicts project duration
by analyzing the sequence of activities with the least scheduling flexibility, known as the

,3|Page


critical path. Float on non-critical activities indicates scheduling flexibility but does not

guarantee on-time completion.

QUESTION 3

During a site inspection, a NYC Department of Buildings inspector observes that a
contractor has installed a site-enclosing fence that is only 6 feet high adjacent to a

public walkway. According to NYC Building Code Chapter 33, what is the minimum
required height for a standard construction fence in this location?

A) 6 feet
B) 8 feet

C) 10 feet
D) 12 feet


CORRECT ANSWER: B

EXPERT RATIONALE: NYC Building Code Section 3307.7 mandates that a site-enclosing

fence must be at least 8 feet high when enclosing a site adjacent to a public walkway. A
6-foot fence does not comply with this requirement.


QUESTION 4
A project manager is preparing a cost estimate for a new NYC municipal building. The

estimate is at a Class 5 level per AACE Cost Estimate Classification. According to DDC
cost estimating templates, what is the minimum design contingency that should be

included?
A) 5%

B) 10%
C) 15%

D) 20%

, 4|Page


CORRECT ANSWER: C


EXPERT RATIONALE: DDC cost estimating templates require a minimum 15% design
contingency for Class 5 estimates, which are high-level estimates used during early

project planning. This contingency accounts for the uncertainty inherent in early-stage
estimates.


QUESTION 5
A contractor on a NYC public works project has submitted a change order request for

additional work. Under the PPB Rules, which of the following is the correct principle
governing contract changes?

A) Change orders are permitted for any work the contractor deems necessary.
B) Change orders are permitted only for work necessary to complete the work included

in the original scope of the contract and for non-material alterations.
C) Change orders are automatically approved if they are under $50,000.

D) Change orders are prohibited once the contract is awarded.

CORRECT ANSWER: B


EXPERT RATIONALE: PPB Rules state that contract changes are permitted only for work
necessary to complete the original scope and for non-material alterations. Material

alterations in the scope of work are not permitted through change orders.

QUESTION 6

A Principal Construction Project Manager is conducting a pre-construction meeting with
a contractor. The contractor asks about the City's policy on prompt payment. Under the

PPB Rules, within how many days must the City pay its bills after receipt of a proper
invoice?
A) 15 days

Document information

Uploaded on
October 5, 2026
Number of pages
138
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$75.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
VerifiedSets
3.7
(7)
Sold
49
Followers
1
Items
2571
Last sold
4 days ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions