1. The owner's project requirements (OPR) document should include✔✔ ANS equipment and system
expectations, energy eflciency requirements, and operational schedules.
2. When starting a commissioning project, the FIRST person added to a project team after an owner's project
manager should be a✔✔ ANS commissioning professional.
3. The owner of several office buildings intends to build a multi-family res-idential building. The owner
intends to use current employees, including property managers and maintenance staff, to operate and
maintain the new building. Which of the following should the commissioning professional do FIRST?✔✔
ANS Determine new facility statt training requirements.
4. During the pre-design stage of the construction of a new surgical hospital, the owner determines that the
commissioning process should include ver-ification of the medical equipment in the owner's project
requirements. A commissioning professional FIRST should modify the✔✔ ANS owner-commissioning professional
agreement.
, 5. A new elementary school will replace a 60-year-old facility and will be oper-ated by the same O&M staff.
The new building will be air conditioned with a high-efficiency, water-cooled chiller and heated with a
condensing boiler. The O&M staff was interviewed and is very proficient with direct expansion (DX)
systems. Which of the following should the commissioning professional do regarding systems maintenance?✔
✔ ANS Suggest that additional training be specified for the new systems.
6. An owner of a museum collection has special temperature and humidity requirements for a new facility
in a cold climate. Temperature setpoint should be maintained within 2 ⁰F (1.1 ⁰C), and relative humidity
should remain within 2.5% of 42.5%. During the pre-design phase, the owner's project requirements are
developed to include these requirements. Which of the following should be done NEXT?✔✔ ANS Confirm that
the basis of design includes these requirements.
7. For newly constructed buildings, the majority of O&M personnel training should be scheduled to occur
after✔✔ ANS performance testing.
8. During project design, a commissioning professional realizes that the level of maintenance required by
the proposed building systems exceeds the cur-rent training of operating staff. The commissioning professional
should✔✔ ANS include training criteria in the contract documents.