ASBESTOS PROJECT DESIGNER EXAM QUESTIONS WIT
QUESTIONS WITH CORRECT ANSWERS 2026
RATED A+
◉ What are the three situations that require a licensed project
designer in a school, public and commercial building? Answer: 1.
Response action other than SSSD
2. Maintenance activity that disturbs ACBM other than SSSD
3. Response action for a major fiber release episode
◉ Class I work definition Answer: Work that involves the removal of
TSI or Surfacing Material (SM)
◉ Class II work definition Answer: Work that involves the removal of
other "low-risk" materials such as roofing, flooring an siding
products
◉ Asbestos abatement projects performed in conjunction with
renovation or demolition of a building require the project designer
to understand what three basic issues? Answer: 1. Scope of the
Asbestos problem
2. Needs of the Building Owner
3. Other Trades
, ◉ What is the Aim of Project Designers? Answer: The safe execution
of high-quality abatement work on schedule and within budget.
◉ ACBM Answer: Surfacing ACM, thermal system insulation ACM, or
miscellaneous ACM that is found in or on interior structural
members or other parts of a school building.
◉ Friable Answer: ACBM that can crushed or turned into a powder
with hand pressure alone
◉ Functional Space Answer: A room, group of rooms, or
homogeneous area designated by a person accredited to prepare
management plans, design abatement projects, or conduct response
actions.
◉ As a Project Designer, can you determine a designated area in a
school?
BONUS: Which kind of licensed asbestos worker(s) CANNOT
determine a designated area in a school? Answer: Answer: Yes
Bonus Answer: Asbestos Inspectors
QUESTIONS WITH CORRECT ANSWERS 2026
RATED A+
◉ What are the three situations that require a licensed project
designer in a school, public and commercial building? Answer: 1.
Response action other than SSSD
2. Maintenance activity that disturbs ACBM other than SSSD
3. Response action for a major fiber release episode
◉ Class I work definition Answer: Work that involves the removal of
TSI or Surfacing Material (SM)
◉ Class II work definition Answer: Work that involves the removal of
other "low-risk" materials such as roofing, flooring an siding
products
◉ Asbestos abatement projects performed in conjunction with
renovation or demolition of a building require the project designer
to understand what three basic issues? Answer: 1. Scope of the
Asbestos problem
2. Needs of the Building Owner
3. Other Trades
, ◉ What is the Aim of Project Designers? Answer: The safe execution
of high-quality abatement work on schedule and within budget.
◉ ACBM Answer: Surfacing ACM, thermal system insulation ACM, or
miscellaneous ACM that is found in or on interior structural
members or other parts of a school building.
◉ Friable Answer: ACBM that can crushed or turned into a powder
with hand pressure alone
◉ Functional Space Answer: A room, group of rooms, or
homogeneous area designated by a person accredited to prepare
management plans, design abatement projects, or conduct response
actions.
◉ As a Project Designer, can you determine a designated area in a
school?
BONUS: Which kind of licensed asbestos worker(s) CANNOT
determine a designated area in a school? Answer: Answer: Yes
Bonus Answer: Asbestos Inspectors