CSM 2030 - Final Exam Questions With
Correct Answers
Which project delivery method best fits the description: The designer
| | | | | | | | | |
and builder hold separate contracts with the owner and a construction
| | | | | | | | | | |
manager is utilized earlier in the project to offer construction knowledge
| | | | | | | | | |
|to the designer during the design phase but is not directly responsible
| | | | | | | | | | | |
for construction. - CORRECT ANSWER✔✔-Construction Manager
| | | | | |
Agency
Which project delivery method best fits the description: The designer,
| | | | | | | | | |
appropriate engineers, and contractor work together with similar goals
| | | | | | | | |
and objectives from the very beginning of the project. Leading a better
| | | | | | | | | | | |
coordinated and more collaborative project. - CORRECT ANSWER✔✔-
| | | | | | |
Integrated Project Delivery | |
Which project delivery method best fits the description: The designer
| | | | | | | | | |
and builder are one entity that is in charge of the design and
| | | | | | | | | | | | |
construction of the project. There is one contract held between the
| | | | | | | | | | |
owner and this entity. - CORRECT ANSWER✔✔-Design-Build
| | | | | |
Which of the following best fits the following description: Temporary
| | | | | | | | | |
sediment control device often staked in the ground with metal posts
| | | | | | | | | | |
and wired backed fabric. - CORRECT ANSWER✔✔-Silt Fence
| | | | | | |
, Which of the following best fits the following description: mulch/seed
| | | | | | | | | |
slurry used to cover large areas of land in a short period of time and
| | | | | | | | | | | | | | |
stabilize the soil against runoff. - CORRECT ANSWER✔✔-Hydroseeding
| | | | | | |
Which of the following best fits the following description: Earthen
| | | | | | | | | |
structure used to allow sediment in water to settle before the water is
| | | | | | | | | | | | |
discharged downstream. - CORRECT ANSWER✔✔-Settling Basin/Pond
| | | | |
Which of the following best fits the following description:
| | | | | | | | |
Environmentally friendly and biodegradable method of erosion control
| | | | | | | |
used for slowing the flow of water and filtering out silt. - CORRECT
| | | | | | | | | | | | |
ANSWER✔✔-Hay Bales |
A three story basement that extends 30' into the ground and is
| | | | | | | | | | | |
supported by strip footings is considered a shallow foundation. -
| | | | | | | | | |
CORRECT ANSWER✔✔-True |
Type VB building codes are very restrictive in terms of size of structure
| | | | | | | | | | | | |
because it allows for the use of almost every material and does not
| | | | | | | | | | | | |
contain requirements for high levels of fire resistance. - CORRECT
| | | | | | | | | |
ANSWER✔✔-True
Correct Answers
Which project delivery method best fits the description: The designer
| | | | | | | | | |
and builder hold separate contracts with the owner and a construction
| | | | | | | | | | |
manager is utilized earlier in the project to offer construction knowledge
| | | | | | | | | |
|to the designer during the design phase but is not directly responsible
| | | | | | | | | | | |
for construction. - CORRECT ANSWER✔✔-Construction Manager
| | | | | |
Agency
Which project delivery method best fits the description: The designer,
| | | | | | | | | |
appropriate engineers, and contractor work together with similar goals
| | | | | | | | |
and objectives from the very beginning of the project. Leading a better
| | | | | | | | | | | |
coordinated and more collaborative project. - CORRECT ANSWER✔✔-
| | | | | | |
Integrated Project Delivery | |
Which project delivery method best fits the description: The designer
| | | | | | | | | |
and builder are one entity that is in charge of the design and
| | | | | | | | | | | | |
construction of the project. There is one contract held between the
| | | | | | | | | | |
owner and this entity. - CORRECT ANSWER✔✔-Design-Build
| | | | | |
Which of the following best fits the following description: Temporary
| | | | | | | | | |
sediment control device often staked in the ground with metal posts
| | | | | | | | | | |
and wired backed fabric. - CORRECT ANSWER✔✔-Silt Fence
| | | | | | |
, Which of the following best fits the following description: mulch/seed
| | | | | | | | | |
slurry used to cover large areas of land in a short period of time and
| | | | | | | | | | | | | | |
stabilize the soil against runoff. - CORRECT ANSWER✔✔-Hydroseeding
| | | | | | |
Which of the following best fits the following description: Earthen
| | | | | | | | | |
structure used to allow sediment in water to settle before the water is
| | | | | | | | | | | | |
discharged downstream. - CORRECT ANSWER✔✔-Settling Basin/Pond
| | | | |
Which of the following best fits the following description:
| | | | | | | | |
Environmentally friendly and biodegradable method of erosion control
| | | | | | | |
used for slowing the flow of water and filtering out silt. - CORRECT
| | | | | | | | | | | | |
ANSWER✔✔-Hay Bales |
A three story basement that extends 30' into the ground and is
| | | | | | | | | | | |
supported by strip footings is considered a shallow foundation. -
| | | | | | | | | |
CORRECT ANSWER✔✔-True |
Type VB building codes are very restrictive in terms of size of structure
| | | | | | | | | | | | |
because it allows for the use of almost every material and does not
| | | | | | | | | | | | |
contain requirements for high levels of fire resistance. - CORRECT
| | | | | | | | | |
ANSWER✔✔-True