This practice test covers weeks 1-5 course materials, which include an introduction to project quality
management, quality planning, quality plan implementation, quality control, process capability analysis,
statistical process control, and quality management systems. Each answer contains detailed
explanations to help you master the course materials. Take notes as you learn as the final exam will
cover week 1-week 6 course materials.
Test Parameters
Logistics: Online
Number of Questions: 10
Duration: 60 minutes
Possible points: 100 points
Questions Type: Fill in the blank, multiple choice, multiple answer, and matching
Question Delivery: One question at a time
Multiple Attempts: Unlimited
Force Completion: Once started, this Test must be completed in one sitting.
Due date: Sunday of the FIFTH week of the course
Take the Quiz Again
Attempt History
Attempt Time Score
KEPT Attempt 2 2 minutes 100 out of 100
LATEST Attempt 3 2 minutes 90 out of 100 *
Attempt 2 2 minutes 100 out of 100
Attempt 1 3 minutes 100 out of 100
* Some questions not yet graded
* Some questions not yet graded
Submitted Dec 3 at 10:23pm
https://northeastern.instructure.com/courses/196393/quizzes/642873 117
, 2024/12/3 22:23 Week 5 Test Your Knowledge (TYK): PUM6135 71779 Project Quality Management SEC 14 Fall 2024 CPS [BOS-B-HY]
Question 1
10/ 10 pts
Peter Panpan is a quality manager at Qualitex LTD, a luxury handbag manufacturer. Peter collects data
from the process and plots them in a time-ordered series. An X-bar chart with points falling above the
upper control limit means that
The process is working much better than expected.
The process is capable of meeting specifications.
Correct!
The process is out of statistical control.
The process is working according to design specifications.
A situation in which the mean of a sample lies above the upper control limit or below the lower control
limit indicates that the process is out of control.
Question 2
10/ 10 pts
Select one of the answer choices to complete the following sentence. Failure costs....
Decrease rapidly as a product or service moves through a production process.
Change rapidly as a product or service moves through a production process.
Vary rapidly as a product or service moves through a production process.
Correct!
Increase rapidly as a product or service moves through a production process.
A general characteristic of failure costs (both internal and external) is that these costs increase rapidly as
a product or service moves through a production process.
Question 3
Not yet graded / 10 pts
In a mean chart for manufacturing process, several points are found to be outside the control limits.
Does this mean that the process is incapable? Explain briefly why or why not, or what else should be
https://northeastern.instructure.com/courses/196393/quizzes/642873 2/7
Week 5_Test Your Knowledge (TYK)
Due No due date
Points 100
Questions 10
Time Limit None
Allowed Attempts Unlimited
Instructions
This practice test covers weeks 1-5 course materials, which include an introduction to project quality
management, quality planning, quality plan implementation, quality control, process capability analysis,
statistical process control, and quality management systems. Each answer contains detailed
explanations to help you master the course materials. Take notes as you learn as the final exam will
cover week 1-week 6 course materials.
Test Parameters
Logistics: Online
Number of Questions: 10
Duration: 60 minutes
Possible points: 100 points
Questions Type: Fill in the blank, multiple choice, multiple answer, and matching
Question Delivery: One question at a time
Multiple Attempts: Unlimited
Force Completion: Once started, this Test must be completed in one sitting.
Due date: Sunday of the FIFTH week of the course
Take the Quiz Again
Attempt History
Attempt Time Score
KEPT Attempt 2 2 minutes 100 out of 100
LATEST Attempt 3 2 minutes 90 out of 100 *
Attempt 2 2 minutes 100 out of 100
Attempt 1 3 minutes 100 out of 100
* Some questions not yet graded
* Some questions not yet graded
Submitted Dec 3 at 10:23pm
https://northeastern.instructure.com/courses/196393/quizzes/642873 117
, 2024/12/3 22:23 Week 5 Test Your Knowledge (TYK): PUM6135 71779 Project Quality Management SEC 14 Fall 2024 CPS [BOS-B-HY]
Question 1
10/ 10 pts
Peter Panpan is a quality manager at Qualitex LTD, a luxury handbag manufacturer. Peter collects data
from the process and plots them in a time-ordered series. An X-bar chart with points falling above the
upper control limit means that
The process is working much better than expected.
The process is capable of meeting specifications.
Correct!
The process is out of statistical control.
The process is working according to design specifications.
A situation in which the mean of a sample lies above the upper control limit or below the lower control
limit indicates that the process is out of control.
Question 2
10/ 10 pts
Select one of the answer choices to complete the following sentence. Failure costs....
Decrease rapidly as a product or service moves through a production process.
Change rapidly as a product or service moves through a production process.
Vary rapidly as a product or service moves through a production process.
Correct!
Increase rapidly as a product or service moves through a production process.
A general characteristic of failure costs (both internal and external) is that these costs increase rapidly as
a product or service moves through a production process.
Question 3
Not yet graded / 10 pts
In a mean chart for manufacturing process, several points are found to be outside the control limits.
Does this mean that the process is incapable? Explain briefly why or why not, or what else should be