Comprehensive Guide With Rationales
A - correct answers Smith construction has won a contract to build a 20-story condominium building in
Auckland. The building will have 70 condos, a parking garage, an indoor and outdoor pool, one floor for
retail, one floor of offices and several shared community rooms. Mary Parker has elected to create a
programme for the creation of the building. Which one of the following best describes a programme?
a. A collection of related projects managed in coordination to gain control that would not necessarily be
available if the projects were managed independently.
b. A standardised approach to project management with multiple projects coordinated together
c. A standardised approach to project management within an organisation
D - correct answers Which of the following choices is not one of the driving forces behind the increasing
demand for project management?
a. Compression of the product life cycle
b. Knowledge explosion
c. Development of third world and closed economies
d. Global warming
e. Corporate downsizing
B - correct answers Which of the following statements describes best the relationship between project
phases and the Project life cycle?
Select one:
a. The Project life cycle includes the time when the project is performed and the expected product
lifespan after that.
b. In project management, the sequence of project phases and phase gates is often referred to as
Project life cycle.
c. The Project life cycle is regarded as a sequence of project activities while phases are defined to control
overlapping activities.
d. The Project life cycle describes how iterations of project management processes are used when a
project schedule is developed.
, E - correct answers In which of the following categories are you more likely to find customer training?
Select one:
a. Defining
b. Planning
c. Executing
d. Reviewing
e. Closing
B - correct answers Among the following activities, which is the best example of a project?
Select one:
a. Completing a college degree
b. Writing a new textbook on project management
c. All of these are good examples of projects
d. Producing automobiles
e. Processing insurance claims
B - correct answers Project managers are not responsible for which one of the following in most
organisations?
Select one:
a. Identifying the project requirements
b. Selecting the projects to be initiated
c. Balancing demands for time, cost scope, and quality
d. Establishing clear and achievable project objectives
B - correct answers Which of the following constraints is not typically found in managing projects?
Select one:
a. Performance
b. Software