ALABAMA CONTRACTOR LICENSING EXAM
1. Which organization administers contractor licensing for
general contractors in Alabama?
A. Alabama Department of Labor
B. Alabama Licensing Board for General Contractors
C. Alabama Building Commission
D. Alabama Department of Revenue
Correct Answer: B. Alabama Licensing Board for
General Contractors
Rationale: The Alabama Licensing Board for General
Contractors is responsible for licensing and regulating general
contractors subject to its jurisdiction.
2. What is the primary purpose of contractor licensing?
A. To increase material prices
B. To regulate construction quality and protect the public
C. To eliminate competition
D. To provide construction financing
, Correct Answer: B. To regulate construction quality
and protect the public
Rationale: Licensing establishes minimum qualifications and
helps protect property owners and the public from unsafe or
incompetent construction practices.
3. Which document generally identifies the scope of
construction work to be performed?
A. Project specifications
B. Payroll register
C. Bank statement
D. Tax return
Correct Answer: A. Project specifications
Rationale: Specifications describe materials, workmanship,
standards, and other requirements governing the work.
4. What is the purpose of a construction contract?
A. To establish the agreement between the parties
B. To replace building codes
, C. To eliminate inspections
D. To determine property taxes
Correct Answer: A. To establish the agreement
between the parties
Rationale: A contract establishes the rights, duties,
responsibilities, scope, price, and other terms agreed upon by
the parties.
5. Which document typically shows the physical arrangement
of rooms and spaces?
A. Floor plan
B. Specification sheet
C. Payroll report
D. Change-order log
Correct Answer: A. Floor plan
Rationale: A floor plan is a drawing that shows the layout of
spaces, walls, openings, fixtures, and other features viewed
from above.
, 6. What does a construction change order normally
accomplish?
A. Changes agreed project requirements
B. Cancels all permits automatically
C. Replaces insurance
D. Establishes employee wages
Correct Answer: A. Changes agreed project
requirements
Rationale: A properly authorized change order documents
modifications to scope, cost, schedule, or other contractual
requirements.
7. What is a building permit primarily intended to accomplish?
A. Authorize regulated construction work
B. Establish a contractor's profit
C. Determine employee benefits
D. Replace construction plans
Correct Answer: A. Authorize regulated construction
work
1. Which organization administers contractor licensing for
general contractors in Alabama?
A. Alabama Department of Labor
B. Alabama Licensing Board for General Contractors
C. Alabama Building Commission
D. Alabama Department of Revenue
Correct Answer: B. Alabama Licensing Board for
General Contractors
Rationale: The Alabama Licensing Board for General
Contractors is responsible for licensing and regulating general
contractors subject to its jurisdiction.
2. What is the primary purpose of contractor licensing?
A. To increase material prices
B. To regulate construction quality and protect the public
C. To eliminate competition
D. To provide construction financing
, Correct Answer: B. To regulate construction quality
and protect the public
Rationale: Licensing establishes minimum qualifications and
helps protect property owners and the public from unsafe or
incompetent construction practices.
3. Which document generally identifies the scope of
construction work to be performed?
A. Project specifications
B. Payroll register
C. Bank statement
D. Tax return
Correct Answer: A. Project specifications
Rationale: Specifications describe materials, workmanship,
standards, and other requirements governing the work.
4. What is the purpose of a construction contract?
A. To establish the agreement between the parties
B. To replace building codes
, C. To eliminate inspections
D. To determine property taxes
Correct Answer: A. To establish the agreement
between the parties
Rationale: A contract establishes the rights, duties,
responsibilities, scope, price, and other terms agreed upon by
the parties.
5. Which document typically shows the physical arrangement
of rooms and spaces?
A. Floor plan
B. Specification sheet
C. Payroll report
D. Change-order log
Correct Answer: A. Floor plan
Rationale: A floor plan is a drawing that shows the layout of
spaces, walls, openings, fixtures, and other features viewed
from above.
, 6. What does a construction change order normally
accomplish?
A. Changes agreed project requirements
B. Cancels all permits automatically
C. Replaces insurance
D. Establishes employee wages
Correct Answer: A. Changes agreed project
requirements
Rationale: A properly authorized change order documents
modifications to scope, cost, schedule, or other contractual
requirements.
7. What is a building permit primarily intended to accomplish?
A. Authorize regulated construction work
B. Establish a contractor's profit
C. Determine employee benefits
D. Replace construction plans
Correct Answer: A. Authorize regulated construction
work