1. What is the primary purpose of a construction contract?
A. To eliminate all project risks
B. To establish the rights, responsibilities, and obligations of the
parties
C. To guarantee a project will finish early
D. To determine employee wages
Answer: B. To establish the rights, responsibilities, and
obligations of the parties
Rationale: A construction contract defines the scope of work,
payment terms, responsibilities, and other contractual
obligations.
2. Which document generally describes the materials,
workmanship, and quality requirements of a project?
A. Specification
B. Payroll register
C. Purchase receipt
D. Timecard
Answer: A. Specification
Rationale: Specifications provide written requirements
concerning materials, installation methods, workmanship, and
quality.
,3. What is the main purpose of a building permit?
A. To establish the contractor's profit
B. To authorize construction under applicable regulations
C. To replace the construction contract
D. To determine material prices
Answer: B. To authorize construction under applicable
regulations
Rationale: Permits provide governmental authorization for
regulated construction work.
4. What does a construction drawing primarily communicate?
A. Employee tax information
B. The design and physical requirements of the work
C. Contractor insurance premiums
D. Supplier credit terms
Answer: B. The design and physical requirements of the work
Rationale: Drawings graphically communicate dimensions,
locations, materials, assemblies, and other project
requirements.
5. What is a change order?
A. A worker's daily schedule
B. A formal modification to the contracted work
C. A supplier invoice
D. A building inspection report
,Answer: B. A formal modification to the contracted work
Rationale: A change order documents an approved change to
scope, price, schedule, or other contract requirements.
6. Which type of estimate is normally prepared before
construction begins to establish expected project costs?
A. Cost estimate
B. Warranty claim
C. Punch list
D. Inspection report
Answer: A. Cost estimate
Rationale: A cost estimate forecasts labor, materials,
equipment, subcontractor, overhead, and other anticipated
expenses.
7. What is direct cost?
A. A cost directly attributable to a specific project activity
B. The contractor's annual tax bill
C. General office rent unrelated to a project
D. Advertising expense
Answer: A. A cost directly attributable to a specific project
activity
Rationale: Direct costs can be assigned specifically to the
project, such as project labor and materials.
8. Which is an example of an indirect construction cost?
A. Concrete installed in a foundation
B. Lumber installed in a wall
, C. General administrative overhead
D. Roofing shingles installed on a roof
Answer: C. General administrative overhead
Rationale: Indirect costs support operations but cannot be
directly assigned to one specific construction activity.
9. What is the purpose of a project schedule?
A. To determine employee tax rates
B. To organize activities and establish expected completion
dates
C. To replace construction drawings
D. To eliminate inspections
Answer: B. To organize activities and establish expected
completion dates
Rationale: Scheduling coordinates work activities, resources,
dependencies, and deadlines.
10. What does a critical path represent in project scheduling?
A. The cheapest group of activities
B. Activities that determine the minimum project duration
C. Only activities performed by subcontractors
D. Optional project activities
Answer: B. Activities that determine the minimum project
duration
Rationale: Delay to a critical-path activity can delay the overall
project unless corrective action is taken.