PMP PMBOK-BASED CERTIFICATION EXAM PRACTICE QUESTIONS AND CORRECT ANSWERS

Content preview

ons

PMP PMBOK-BASED CERTIFICATION EXAM PRACTICE QUESTIONS AND
CORRECT ANSWERS (VERIFIED ANSWERS) PLUS RATIONALE Q&

Batch 1: Questions 1–50

1. A project manager is leading a software development project. The
sponsor asks for the project's key deliverables and milestones. Which
document should the project manager reference?



A) Project charter

B) Project management plan

C) Work breakdown structure

D) Project scope statement



Correct Answer: B) Project management plan



Rationale: The project management plan integrates all subsidiary plans,
including the scope, schedule, and baseline documents that define
deliverables and milestones. The project charter authorizes the project
but does not contain detailed deliverables or milestones. The WBS
breaks down work but does not itself list milestones. The scope
statement defines boundaries but not the full schedule.

,2. During project execution, a team member identifies a risk that was
not previously documented. What should the project manager do
FIRST?



A) Escalate to the sponsor

B) Update the risk register

C) Implement a workaround

D) Add contingency reserve



Correct Answer: B) Update the risk register



Rationale: Newly identified risks should first be documented in the risk
register as part of the Identify Risks process. Escalation may be needed
later if the risk is beyond the project manager's authority. A
workaround is used for unplanned risks that have already occurred.
Contingency reserve is used for known risks.



3. A project manager wants to ensure that quality is built into the
product rather than inspected at the end. Which approach best
supports this?



A) Quality control inspections

,B) Statistical sampling

C) Quality assurance audits

D) Prevention over inspection



Correct Answer: D) Prevention over inspection



Rationale: PMBOK emphasizes "prevention over inspection" as a core
quality principle. Quality should be planned, designed, and built into
the product. Quality control and inspections detect defects after the
fact. Statistical sampling is a QC technique. Audits verify compliance but
do not inherently prevent defects.



4. Which document formally authorizes the existence of a project and
provides the project manager with authority to apply organizational
resources?



A) Project management plan

B) Business case

C) Project charter

D) Benefits management plan

, Correct Answer: C) Project charter



Rationale: The project charter formally authorizes the project and gives
the project manager authority. The business case justifies the project.
The benefits management plan describes how benefits will be
delivered. The project management plan describes how the project will
be executed.



5. A project manager is estimating activity durations using historical
data from similar projects. Which technique is being used?



A) Parametric estimating

B) Analogous estimating

C) Three-point estimating

D) Bottom-up estimating



Correct Answer: B) Analogous estimating



Rationale: Analogous estimating uses historical data from similar
projects. Parametric estimating uses statistical relationships. Three-
point estimating uses optimistic, pessimistic, and most likely estimates.

Document information

Uploaded on
September 26, 2026
Number of pages
143
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$29.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
supergrader
4.3
(3)
Sold
13
Followers
0
Items
3320
Last sold
1 week ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions