1. A program manager is reviewing the program's business case and
discovers that a recent regulatory change has made one of the planned
benefits obsolete. What should the program manager do FIRST?
A. Continue with the original benefits plan to avoid disruption
B. Update the benefits register and assess the impact on strategic
alignment
C. Immediately terminate the program
D. Escalate the issue to the project managers for resolution
Correct Answer: B
Rationale: The program manager must continuously monitor the
business environment and assess how changes affect benefit
realization and strategic alignment. Updating the benefits register and
conducting an impact analysis is the appropriate first step before
recommending any major decision.
,2. Which of the following BEST describes the distinction between
program outputs and program benefits?
A. Outputs are tangible deliverables; benefits are the measurable value
realized from those outputs
B. Outputs are strategic; benefits are operational
C. Outputs are managed at the program level; benefits are managed at
the project level
D. Outputs and benefits are interchangeable terms in program
management
Correct Answer: A
Rationale: Projects produce outputs (deliverables), while programs
deliver outcomes and benefits—the measurable value that results from
the outputs being utilized. This distinction is fundamental to program
management.
3. A program manager is developing the program roadmap. What is the
PRIMARY purpose of this document?
A. To assign individual tasks to project team members
,B. To provide a high-level view of the program's projects, their
interdependencies, and benefit delivery over time
C. To replace the need for individual project schedules
D. To document detailed resource allocations for each component
Correct Answer: B
Rationale: The program roadmap provides a high-level visual
representation of the program's components, their sequencing,
interdependencies, and the timeline for benefit realization. It is a
strategic planning tool, not a detailed execution document.
4. During a strategic alignment review, the program manager identifies
that a component project's objectives no longer support the program's
strategic goals. What is the MOST appropriate action?
A. Allow the project to continue since it is already funded
B. Recommend to the governance board that the component be
realigned or terminated
C. Ask the project manager to modify the project without program
oversight
D. Wait until the next scheduled program review to address the issue
, Correct Answer: B
Rationale: The program manager is responsible for maintaining
alignment between components and strategic objectives. If a
component no longer supports the program, this should be escalated
to the governance board for a formal decision.
5. Which of the following is a key input to the program's strategic
alignment activities?
A. Individual project risk registers
B. Organizational strategic objectives and business environment
analysis
C. Team member performance reviews
D. Detailed project schedules
Correct Answer: B
Rationale: Strategic alignment requires understanding the
organization's strategic direction and the external business
QUESTIONS AND CORRECT ANSWERS (VERIFIED ANSWERS) PLUS
RATIONALE
1. A program manager is reviewing the program's business case and
discovers that a recent regulatory change has made one of the planned
benefits obsolete. What should the program manager do FIRST?
A. Continue with the original benefits plan to avoid disruption
B. Update the benefits register and assess the impact on strategic
alignment
C. Immediately terminate the program
D. Escalate the issue to the project managers for resolution
Correct Answer: B
Rationale: The program manager must continuously monitor the
business environment and assess how changes affect benefit
realization and strategic alignment. Updating the benefits register and
conducting an impact analysis is the appropriate first step before
recommending any major decision.
,2. Which of the following BEST describes the distinction between
program outputs and program benefits?
A. Outputs are tangible deliverables; benefits are the measurable value
realized from those outputs
B. Outputs are strategic; benefits are operational
C. Outputs are managed at the program level; benefits are managed at
the project level
D. Outputs and benefits are interchangeable terms in program
management
Correct Answer: A
Rationale: Projects produce outputs (deliverables), while programs
deliver outcomes and benefits—the measurable value that results from
the outputs being utilized. This distinction is fundamental to program
management.
3. A program manager is developing the program roadmap. What is the
PRIMARY purpose of this document?
A. To assign individual tasks to project team members
,B. To provide a high-level view of the program's projects, their
interdependencies, and benefit delivery over time
C. To replace the need for individual project schedules
D. To document detailed resource allocations for each component
Correct Answer: B
Rationale: The program roadmap provides a high-level visual
representation of the program's components, their sequencing,
interdependencies, and the timeline for benefit realization. It is a
strategic planning tool, not a detailed execution document.
4. During a strategic alignment review, the program manager identifies
that a component project's objectives no longer support the program's
strategic goals. What is the MOST appropriate action?
A. Allow the project to continue since it is already funded
B. Recommend to the governance board that the component be
realigned or terminated
C. Ask the project manager to modify the project without program
oversight
D. Wait until the next scheduled program review to address the issue
, Correct Answer: B
Rationale: The program manager is responsible for maintaining
alignment between components and strategic objectives. If a
component no longer supports the program, this should be escalated
to the governance board for a formal decision.
5. Which of the following is a key input to the program's strategic
alignment activities?
A. Individual project risk registers
B. Organizational strategic objectives and business environment
analysis
C. Team member performance reviews
D. Detailed project schedules
Correct Answer: B
Rationale: Strategic alignment requires understanding the
organization's strategic direction and the external business