CMGT 2400 Test 1-Questions with Correct
Answers
Project delivery phases
Predesign, design, preconstruction, construction, postconstruction
Planning phase of project delivery, function and purpose of building
Predesign
Phase of project delivery that begins after the architect is selected
Design
Phase of project delivery after drawings and specs have been completed, scheduled,
when subs are hired
Preconstruction
Phase of project delivery that begins after the GC has been selected
Construction
Phase of project delivery when occupants can occupy the building
Postconstruction
What is the first step of the project delivery process?
Building program
What is civil work?
, Site work, draining, grading
What does M(H)EPF stand for?
Mechanical, HVAC, electrical, plumbing, fire protection
What does the typical design team look like
Owner
Architect
Civil/structural, MEPF, other consultants
What is a type 1 building?
Most fire resistant
What is a type 5 building?
Least fire resistant
What is a geotechnical consultant?
Soil testing
What are the components of the design development phase?
Schematic design, design development, construction documents
What is a sketch of the graphic shape of the building?
Schematic design
What develops a practical and pragmatic solution?
Answers
Project delivery phases
Predesign, design, preconstruction, construction, postconstruction
Planning phase of project delivery, function and purpose of building
Predesign
Phase of project delivery that begins after the architect is selected
Design
Phase of project delivery after drawings and specs have been completed, scheduled,
when subs are hired
Preconstruction
Phase of project delivery that begins after the GC has been selected
Construction
Phase of project delivery when occupants can occupy the building
Postconstruction
What is the first step of the project delivery process?
Building program
What is civil work?
, Site work, draining, grading
What does M(H)EPF stand for?
Mechanical, HVAC, electrical, plumbing, fire protection
What does the typical design team look like
Owner
Architect
Civil/structural, MEPF, other consultants
What is a type 1 building?
Most fire resistant
What is a type 5 building?
Least fire resistant
What is a geotechnical consultant?
Soil testing
What are the components of the design development phase?
Schematic design, design development, construction documents
What is a sketch of the graphic shape of the building?
Schematic design
What develops a practical and pragmatic solution?