Updating is needed for projects that have duration of at least one year or a
minimum budge of 1 million dollars
False
Project monitoring is only a part of project control
true
Data date is the date all information was entered in the computer
False
In updating schedules we must not only enter work progress but we must also enter
any changes to future work
true
A baseline schedule is a schedule with every activity loaded with required resources
and budge
False
It is always a good idea to accelerate projects
False
it is always a good idea to study project acceleration and its impact on cost
Answers
Updating is needed for projects that have duration of at least one year or a
minimum budge of 1 million dollars
False
Project monitoring is only a part of project control
true
Data date is the date all information was entered in the computer
False
In updating schedules we must not only enter work progress but we must also enter
any changes to future work
true
A baseline schedule is a schedule with every activity loaded with required resources
and budge
False
It is always a good idea to accelerate projects
False
it is always a good idea to study project acceleration and its impact on cost