spill prevention equipment consists of a spill bucket that is intended for....
Correct Answer: Catching product when transfer hose is detached.
• Question
Which statement regarding manual inventory reconciliation is true.....
Correct Answer: it is no longer an approved method of non-visual monitoring of existing
UST systems.
• Question
An approved method of leak detection for an underground pressurized piping system
includes...
Correct Answer: A device that automatically restricts product flow through piping.
• Question
Under Dispenser Containment was required for all UST systems by
Correct Answer: 12/31/2003
• Question
Tanks without secondary containment located within______of a public drinking water well
require recurrent enhanced leak detection testing
Correct Answer: 1,000 Feet
• Question
The term Ullage means
Correct Answer: The space or volume above the level of motor vehicle fuel in a tank or
tank system
• Question
During a monitor system certification all of the following must be inspected except
Correct Answer: Fire extinguisher location
• Question
When an electrically conductive object is grounded, the electric potential is
Correct Answer: zero
, • Question
A_____is installed on the vent riser to prevent vapors from escaping or entering the
system, unless a pressure or vacuum condition exists that exceeds that design opening
pressure or vacuum limit of the cap
Correct Answer: P/V Cap
• Question
According to the health and safety code, Tanks installed after July 1, 2003 require a one
time test at installation to determine that the tank is product tight. acceptable methods
are
Correct Answer: inert gas pressure test
• Question
Spell containment devices must be attested no less than ________ To demonstrate that it
is capable Of containing the hazardous substance until it is detected in cleaned-up
Correct Answer: Annually
• Question
Spill containment structure or spill bucket is required at the
Correct Answer: fill
• Question
Given a monitoring system certification is being conducted on a ust System with
double-wall tank and single walled pressurized piping a positive shut off device is used
for overfill protection to complete the monitoring system certification the service
technician must functionally test all of the following components except the
Correct Answer: Automatic tank gauge
• Question
All of the following must be included VST monitor system certification except the
Correct Answer: fuctionality of flapper were ball
• Question
According to the ccr title 23 UST regulations a monitoring equipment certification must
be documented using a
Correct Answer: Monitoring system certification form
• Question
Emergency shutoff valve or shear valves Shall be installed at what location
Correct Answer: At-grade level of dispenser device
Answers Latest Updated 2026/2027 (Graded A+)
• Question
spill prevention equipment consists of a spill bucket that is intended for....
Correct Answer: Catching product when transfer hose is detached.
• Question
Which statement regarding manual inventory reconciliation is true.....
Correct Answer: it is no longer an approved method of non-visual monitoring of existing
UST systems.
• Question
An approved method of leak detection for an underground pressurized piping system
includes...
Correct Answer: A device that automatically restricts product flow through piping.
• Question
Under Dispenser Containment was required for all UST systems by
Correct Answer: 12/31/2003
• Question
Tanks without secondary containment located within______of a public drinking water well
require recurrent enhanced leak detection testing
Correct Answer: 1,000 Feet
• Question
The term Ullage means
Correct Answer: The space or volume above the level of motor vehicle fuel in a tank or
tank system
• Question
During a monitor system certification all of the following must be inspected except
Correct Answer: Fire extinguisher location
• Question
When an electrically conductive object is grounded, the electric potential is
Correct Answer: zero
, • Question
A_____is installed on the vent riser to prevent vapors from escaping or entering the
system, unless a pressure or vacuum condition exists that exceeds that design opening
pressure or vacuum limit of the cap
Correct Answer: P/V Cap
• Question
According to the health and safety code, Tanks installed after July 1, 2003 require a one
time test at installation to determine that the tank is product tight. acceptable methods
are
Correct Answer: inert gas pressure test
• Question
Spell containment devices must be attested no less than ________ To demonstrate that it
is capable Of containing the hazardous substance until it is detected in cleaned-up
Correct Answer: Annually
• Question
Spill containment structure or spill bucket is required at the
Correct Answer: fill
• Question
Given a monitoring system certification is being conducted on a ust System with
double-wall tank and single walled pressurized piping a positive shut off device is used
for overfill protection to complete the monitoring system certification the service
technician must functionally test all of the following components except the
Correct Answer: Automatic tank gauge
• Question
All of the following must be included VST monitor system certification except the
Correct Answer: fuctionality of flapper were ball
• Question
According to the ccr title 23 UST regulations a monitoring equipment certification must
be documented using a
Correct Answer: Monitoring system certification form
• Question
Emergency shutoff valve or shear valves Shall be installed at what location