1. In a Fixed Price Incentive Fee (FPIF) contract, the ‘Point of Total Assumption’ (PTA) is
reached when:
A. The seller’s profit is maximized.
B. The ceiling price is equal to the target cost.
C. The buyer and seller share the cost overrun equally.
D. The seller bears all cost overruns for every additional dollar spent.
Answer: D
Conceptual Explanation: The Point of Total Assumption (PTA) is the point in an incentive-
bearing contract where the seller assumes responsibility for all cost overruns. Beyond this
point, the seller’s profit decreases by $1 for every $1 of cost overrun.
2. According to the ‘Rule of Seven’ in Control Charts, what action should the project manager
take?
A. Investigate the process for a non-random cause.
,B. Recalibrate the equipment immediately.
C. Ignore it as long as the points are within the control limits.
D. Increase the sample size to verify the trend.
Answer: A
Conceptual Explanation: The Rule of Seven states that if seven consecutive data points fall
on one side of the mean, even if within control limits, the process is considered out of
control and requires investigation for an assignable cause.
3. Which motivation theory suggests that ‘hygiene factors’ do not motivate, but their absence
can lead to dissatisfaction?
A. Maslow’s Hierarchy of Needs
B. McClelland’s Theory of Needs
C. Herzberg’s Two-Factor Theory
D. McGregor’s Theory X and Theory Y
Answer: C
Conceptual Explanation: Herzberg’s Two-Factor Theory distinguishes between
motivators (e.g., achievement) and hygiene factors (e.g., salary, working conditions).
Hygiene factors prevent dissatisfaction but do not provide long-term motivation.
4. A project has 12 stakeholders. How many communication channels exist?
A. 132
, B. 66
C. 144
D. 72
Answer: B
Conceptual Explanation: The formula for communication channels is n(n-1)/2. For 12
stakeholders: 12 * = 66.
5. During a risk assessment, you calculate an Expected Monetary Value (EMV). If a risk has a
20% probability of causing a $50,000 loss and a 10% probability of causing a $20,000 gain,
what is the total EMV?
A. -$10,000
B. $8,000
C. -$8,000
D. $12,000
Answer: C
Conceptual Explanation: EMV = (Probability * Impact). EMV = (0.20 * -50,000) + (0.10 *
20,000) = -10,000 + 2,000 = -$8,000.
6. Which conflict resolution technique results in a ‘lose-lose’ situation?
A. Collaborating/Problem Solving
B. Compromising/Reconciling
MANAGEMENT EXAM 4 QUESTIONS
AND ANSWERS WITH VERIFIED
SOLUTIONS 2026/2027 UPDATE. JUST
RELEASED
1. In a Fixed Price Incentive Fee (FPIF) contract, the ‘Point of Total Assumption’ (PTA) is
reached when:
A. The seller’s profit is maximized.
B. The ceiling price is equal to the target cost.
C. The buyer and seller share the cost overrun equally.
D. The seller bears all cost overruns for every additional dollar spent.
Answer: D
Conceptual Explanation: The Point of Total Assumption (PTA) is the point in an incentive-
bearing contract where the seller assumes responsibility for all cost overruns. Beyond this
point, the seller’s profit decreases by $1 for every $1 of cost overrun.
2. According to the ‘Rule of Seven’ in Control Charts, what action should the project manager
take?
A. Investigate the process for a non-random cause.
,B. Recalibrate the equipment immediately.
C. Ignore it as long as the points are within the control limits.
D. Increase the sample size to verify the trend.
Answer: A
Conceptual Explanation: The Rule of Seven states that if seven consecutive data points fall
on one side of the mean, even if within control limits, the process is considered out of
control and requires investigation for an assignable cause.
3. Which motivation theory suggests that ‘hygiene factors’ do not motivate, but their absence
can lead to dissatisfaction?
A. Maslow’s Hierarchy of Needs
B. McClelland’s Theory of Needs
C. Herzberg’s Two-Factor Theory
D. McGregor’s Theory X and Theory Y
Answer: C
Conceptual Explanation: Herzberg’s Two-Factor Theory distinguishes between
motivators (e.g., achievement) and hygiene factors (e.g., salary, working conditions).
Hygiene factors prevent dissatisfaction but do not provide long-term motivation.
4. A project has 12 stakeholders. How many communication channels exist?
A. 132
, B. 66
C. 144
D. 72
Answer: B
Conceptual Explanation: The formula for communication channels is n(n-1)/2. For 12
stakeholders: 12 * = 66.
5. During a risk assessment, you calculate an Expected Monetary Value (EMV). If a risk has a
20% probability of causing a $50,000 loss and a 10% probability of causing a $20,000 gain,
what is the total EMV?
A. -$10,000
B. $8,000
C. -$8,000
D. $12,000
Answer: C
Conceptual Explanation: EMV = (Probability * Impact). EMV = (0.20 * -50,000) + (0.10 *
20,000) = -10,000 + 2,000 = -$8,000.
6. Which conflict resolution technique results in a ‘lose-lose’ situation?
A. Collaborating/Problem Solving
B. Compromising/Reconciling