In what type of organization does the project manager have little or no authority?
Functional
Weak Matrix
Balanced Matrix
Projectized - correct answer-Functional
In what type of organization is the functional manager likely to maintain project
budget control?
Weak Matrix
Strong Matrix
Balanced Matrix
Projectized - correct answer-Weak Matrix
In what type of organization does each employee have one clear superior and is
grouped by specialty such as sales, marketing, engineering, accounting, etc.?
Functional
Weak Matrix
, Projectized
Balanced Matrix - correct answer-Functional
In what type of organization is the Project Coordinator likely to be a part-time
with almost no administrative support?
Functional
Weal Matrix
Balanced Matrix
Projectized - correct answer-Functional
In what type of organization is the project manager likely to have a variety of
possible budgetary control models?
Functional
Projectized
Balanced Matrix
Any of the above - correct answer-Balanced Matrix
Sally is a frustrated project coordinator. All of her resources split their time
between operational responsibility and project work. It seems she can only get
about 10% to 15% if their time. She also has very limited authority, and has very
little administrative support. In what kind of organization does Sally work?
Balanced Matrix
Functional
Strong Matrix
Weal Matrix - correct answer-Weak Matrix
Review Questions & Verified Answers |
2026/2027
In what type of organization does the project manager have little or no authority?
Functional
Weak Matrix
Balanced Matrix
Projectized - correct answer-Functional
In what type of organization is the functional manager likely to maintain project
budget control?
Weak Matrix
Strong Matrix
Balanced Matrix
Projectized - correct answer-Weak Matrix
In what type of organization does each employee have one clear superior and is
grouped by specialty such as sales, marketing, engineering, accounting, etc.?
Functional
Weak Matrix
, Projectized
Balanced Matrix - correct answer-Functional
In what type of organization is the Project Coordinator likely to be a part-time
with almost no administrative support?
Functional
Weal Matrix
Balanced Matrix
Projectized - correct answer-Functional
In what type of organization is the project manager likely to have a variety of
possible budgetary control models?
Functional
Projectized
Balanced Matrix
Any of the above - correct answer-Balanced Matrix
Sally is a frustrated project coordinator. All of her resources split their time
between operational responsibility and project work. It seems she can only get
about 10% to 15% if their time. She also has very limited authority, and has very
little administrative support. In what kind of organization does Sally work?
Balanced Matrix
Functional
Strong Matrix
Weal Matrix - correct answer-Weak Matrix