BICSI RTPM ANSWERS AND QUESTIONS SET A+
✔✔Project closeout tasks include - ✔✔Submittals
Documenting device information
Patching matrix
Punch list
Final Invoice
Lessons Learned (GC, Owner)
Warranties
Final Walk
Training end users
Transmittal
✔✔Submittals include - ✔✔Photos
Test results
Naming conventions
As-Builts
✔✔OSP Pre-Site Survey Considerations - ✔✔Obtain all documentation
Obtain work safety from AHJ
Pole Attachment
Contact One-Call System to locate existing utilities
✔✔Locating Utilities is the responsibility of the ____________________ - ✔✔Private
Property Owner
✔✔Private Property Owner can demand that ________________ locates utilities -
✔✔Exacavator
✔✔OSP Site Survey - ✔✔Mark up print with specific observations
Provide second print to mark up pathways
Determine best entrance point
✔✔OSP Post Site Survey Tasks - ✔✔Prepare issuable documents
Prepare cost estimates
, ✔✔OSP Pre Construction - ✔✔Meeting with first responder
One call system
Private property owner to locate utilities
Permits
✔✔OSP Construction Phases - ✔✔Track project progress
Examine daily field reports
As Builts
Punch list - onsite contractor
Final walkthrough
Manage pay requests
✔✔Who is included in the final OSP walkthrough - ✔✔General Contractor
Client
Onsite Contractor
✔✔OSP Post Construction - ✔✔Compile and turnover completion package to client
(As builts, test results, instruction manuals, warranties, commissioning reports)
In house Lessons Learned
✔✔OSP Design Checklist Reference # - ✔✔1 - Title Block
2 - Required Information
3 - Electronic Telecommunication Equipment
4 - Notes
5 - Aerial Environment
6 - Direct Buried Environment
7 - Conduit Envirnoment
8 - Undergorund Envirnoment
9 - Miscellaneous
✔✔OSP Cost Estimating - ✔✔Special Equipment - hourly and materials (cranes)
Labor - hourly unit
Materials - item cost and delivery
Restoration - hourly and material/ unit (asphalt, concrete, grass)
Permits - fees (designer, inspector, as builts)
✔✔Project Drawing starts with P - ✔✔Plumbing
✔✔Project Drawing starts with U - ✔✔Utilities
✔✔Project Drawing starts with M - ✔✔Mechanical
✔✔Project Drawing starts with A - ✔✔Architectural
✔✔Project closeout tasks include - ✔✔Submittals
Documenting device information
Patching matrix
Punch list
Final Invoice
Lessons Learned (GC, Owner)
Warranties
Final Walk
Training end users
Transmittal
✔✔Submittals include - ✔✔Photos
Test results
Naming conventions
As-Builts
✔✔OSP Pre-Site Survey Considerations - ✔✔Obtain all documentation
Obtain work safety from AHJ
Pole Attachment
Contact One-Call System to locate existing utilities
✔✔Locating Utilities is the responsibility of the ____________________ - ✔✔Private
Property Owner
✔✔Private Property Owner can demand that ________________ locates utilities -
✔✔Exacavator
✔✔OSP Site Survey - ✔✔Mark up print with specific observations
Provide second print to mark up pathways
Determine best entrance point
✔✔OSP Post Site Survey Tasks - ✔✔Prepare issuable documents
Prepare cost estimates
, ✔✔OSP Pre Construction - ✔✔Meeting with first responder
One call system
Private property owner to locate utilities
Permits
✔✔OSP Construction Phases - ✔✔Track project progress
Examine daily field reports
As Builts
Punch list - onsite contractor
Final walkthrough
Manage pay requests
✔✔Who is included in the final OSP walkthrough - ✔✔General Contractor
Client
Onsite Contractor
✔✔OSP Post Construction - ✔✔Compile and turnover completion package to client
(As builts, test results, instruction manuals, warranties, commissioning reports)
In house Lessons Learned
✔✔OSP Design Checklist Reference # - ✔✔1 - Title Block
2 - Required Information
3 - Electronic Telecommunication Equipment
4 - Notes
5 - Aerial Environment
6 - Direct Buried Environment
7 - Conduit Envirnoment
8 - Undergorund Envirnoment
9 - Miscellaneous
✔✔OSP Cost Estimating - ✔✔Special Equipment - hourly and materials (cranes)
Labor - hourly unit
Materials - item cost and delivery
Restoration - hourly and material/ unit (asphalt, concrete, grass)
Permits - fees (designer, inspector, as builts)
✔✔Project Drawing starts with P - ✔✔Plumbing
✔✔Project Drawing starts with U - ✔✔Utilities
✔✔Project Drawing starts with M - ✔✔Mechanical
✔✔Project Drawing starts with A - ✔✔Architectural