BICSI RTPM ACTUAL FINALS ANSWERS AND
QUESTIONS SET A+
✔✔Objectives of the design phase during commissioning include: - ✔✔Architectural
review of the building
Review of the IT and Facilities System
Execution of needs assessment
Submission of design intent documentation
Review SoW for all participants and contractors
Review systems for maintainability
✔✔Commissioning Construction Phase - ✔✔Commissioning authority monitors the
progress to ensure design's intent
✔✔Objectives of the construction phase during commissioning include: -
✔✔Performance of milestone monitoring
Completion of prefunctional testing as required
Submission of field inspection and progress reports
Monitoring of the change order process
Documentation and approval of any mod to the design's intent
✔✔Commissioning Acceptance Phase - ✔✔Functional performance testing / System
calibration are completed and documented
✔✔Objectives of the acceptance phase during commissioning include: - ✔✔Baseline
performance documentation
Functional performance testing
Site audit
Warranty audit
Submission of the final documentation and all tests reports
✔✔Commissioning Post-Acceptance - ✔✔Operations and Maintainance procedures
defined
, ✔✔Objectives of post-acceptance during commissioning include: - ✔✔Establishment of
Operations & Maintainance
Document storage and modifications to documents
Personnel Training
Establishment of MACD procedures
Implementation of change control procedures and policies
✔✔Types of New Commissioning - ✔✔Continuous
Milestone
Acceptance
Network
✔✔Types of Existing Building Commissioning - ✔✔Retrocommissioning - for the first
time
Recommissioning - second time
✔✔Commissioning Design Documents - ✔✔• Design intent.
• Basis of design.
• Building drawings.
• General equipment specifications.
• System submittals.
• Architectural requirements.
• Project owner's requirements.
• Change orders.
• Sequence of operation.
✔✔Commissioning Process Documents - ✔✔• Commissioning plan.
• Reporting forms.
• Schedules and time lines.
• Meeting minutes and progress reporting.
• Conflict and resolution records.
• Startup and testing plans and schedule.
• Training program.
✔✔Commissioning Verification Documents - ✔✔• Construction observation reports.
• Commissioning issues log.
• Test reports from:
- Manufacturers
- Contractor
- Commissioning agent
• Final commissioning report.
✔✔Final Commissioning Report - ✔✔Project name.
• Name, address, firm, and telephone number of commissioning authority.
• Description of the building:
QUESTIONS SET A+
✔✔Objectives of the design phase during commissioning include: - ✔✔Architectural
review of the building
Review of the IT and Facilities System
Execution of needs assessment
Submission of design intent documentation
Review SoW for all participants and contractors
Review systems for maintainability
✔✔Commissioning Construction Phase - ✔✔Commissioning authority monitors the
progress to ensure design's intent
✔✔Objectives of the construction phase during commissioning include: -
✔✔Performance of milestone monitoring
Completion of prefunctional testing as required
Submission of field inspection and progress reports
Monitoring of the change order process
Documentation and approval of any mod to the design's intent
✔✔Commissioning Acceptance Phase - ✔✔Functional performance testing / System
calibration are completed and documented
✔✔Objectives of the acceptance phase during commissioning include: - ✔✔Baseline
performance documentation
Functional performance testing
Site audit
Warranty audit
Submission of the final documentation and all tests reports
✔✔Commissioning Post-Acceptance - ✔✔Operations and Maintainance procedures
defined
, ✔✔Objectives of post-acceptance during commissioning include: - ✔✔Establishment of
Operations & Maintainance
Document storage and modifications to documents
Personnel Training
Establishment of MACD procedures
Implementation of change control procedures and policies
✔✔Types of New Commissioning - ✔✔Continuous
Milestone
Acceptance
Network
✔✔Types of Existing Building Commissioning - ✔✔Retrocommissioning - for the first
time
Recommissioning - second time
✔✔Commissioning Design Documents - ✔✔• Design intent.
• Basis of design.
• Building drawings.
• General equipment specifications.
• System submittals.
• Architectural requirements.
• Project owner's requirements.
• Change orders.
• Sequence of operation.
✔✔Commissioning Process Documents - ✔✔• Commissioning plan.
• Reporting forms.
• Schedules and time lines.
• Meeting minutes and progress reporting.
• Conflict and resolution records.
• Startup and testing plans and schedule.
• Training program.
✔✔Commissioning Verification Documents - ✔✔• Construction observation reports.
• Commissioning issues log.
• Test reports from:
- Manufacturers
- Contractor
- Commissioning agent
• Final commissioning report.
✔✔Final Commissioning Report - ✔✔Project name.
• Name, address, firm, and telephone number of commissioning authority.
• Description of the building: