Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Document preview thumbnail
Preview 3 out of 17 pages
Exam (elaborations)

BICSI RTPM CORRECT EXAMS ANSWERS AND QUESTIONS SET A.pdf

Document preview thumbnail
Preview 3 out of 17 pages

BICSI RTPM CORRECT EXAMS ANSWERS AND QUESTIONS SET A.pdf

Content preview

BICSI RTPM CORRECT EXAMS ANSWERS AND
QUESTIONS SET A+
✔✔How do you assess a risk - ✔✔Analysis: Probability/ Impact
Identify: What, when, how can go wrong
Mitigation :Tolerance/ Contingeny

✔✔Systematically identify risks by - ✔✔Lessons Learned
Previous data
Brainstorming / SWOT chart
Cause and Effect Diagram

✔✔Risk Identification Process - ✔✔Should be done with as many key individuals as
possible

✔✔Risk information is derived from - ✔✔Analysis of high level deliverables
Analysis of WBS and Network Diagram
Analysis of Change Request
Project Team Input
Stakeholders Input

✔✔Risk Triggers - ✔✔Events that warn of occurance of risks
These are determined during risk identification

✔✔Risk Analysis Methods - ✔✔Qualitative and Quantitative

✔✔Qualitative Risk Analysis - ✔✔Qualifies the expected impact of cost, time, quality
(Hi, Mid, Low)

✔✔Quantitative Risk Analysis - ✔✔measuring the probability and consequences of risks
as well as estimating their implications for the project objectives. Rank and multiply

✔✔Risk Severity Grid - ✔✔Captures Quantitative analysis, (time, cost, quality, risk
proximity)

,✔✔Risk Planning Mitigation Techniques - ✔✔Avoidance
Sharing
Transference
Moderation
Acceptance

✔✔Stakeholder MGMT - ✔✔Each Stakeholder must be analyzed: how they affect/
affected by the project.
Stakeholders are given a rank based on their authority/ interest level

✔✔Developing an Organizational Breakdown Structure (OBS) - ✔✔Identify people and
organizations needed to complete the project
Shows responsibility for other team members, let's everyone know their role and
includes phone#, email, clients team

✔✔Work Breakdown Structure - ✔✔Must cover projects end product and:
Planning the project
Implementing the project
Closing out the project
Diagrammed as tree or outline structure
(Should be very specific)

✔✔Developing a schedule using PERT - ✔✔Network diagrams to identify predecessor
and successor relationships

✔✔What are the dependencies of PERT - ✔✔Finish - Start
Finish - Finish
Start - Finish
Start - Start

✔✔Analogus Estimates - ✔✔Based on similar work done in the past

✔✔Parametric Estimates - ✔✔dollar/ foot

✔✔Engineering Estimates - ✔✔Developed by client

✔✔Subcontractor Estimates - ✔✔Special tools and skills

✔✔Definitive Estimates - ✔✔Based on Materials and Labor

✔✔Bottom-Up Estimates - ✔✔Uses WBS Tasks

✔✔Pert Estimates - ✔✔(Optimistic + (Most Likely*4) + Pessimestic)/6

, ✔✔Four Versions of the Schedule Using the PERT Formula - ✔✔Optimistic View
Most Likely View
Pessimistic View
PERT View

✔✔Planned Value (PV) - ✔✔The authorized budget assigned to scheduled work.
Formerly known as BCWS
The total value for the project is Budget @ Completion

✔✔Earned Value (EV) - ✔✔The measure of work performed

✔✔Actual Costs (AC) - ✔✔Amount of money it took to accomplish the work that was
completed.
Goal should be to = PV

✔✔Cost Variance (CV) - ✔✔The amount of budget deficit or surplus at a given point in
time, expressed as the difference between the earned value and the actual cost.
= EV - AC
Cost baseline comparrison
0 = target
Deficit < 0 > Surplus

✔✔Schedule Variance (SV) - ✔✔A measure of schedule performance expressed as the
difference between the earned value and the planned value.
= EV - PV
Target = 0
Behind Schedule < 0 > Ahead of Schedule

✔✔Cost Performance Index (CPI) - ✔✔A measure of the cost efficiency of budgeted
resources expressed as the ratio of earned value to actual cost.
= EV / AC
Target = 1; 0.95 - 1.05
Over Budget < 1 > Under Budget
Under .90 and above 1.1 is bad

✔✔Schedule Performance Index (SPI) - ✔✔A measure of schedule efficiency
expressed as the ratio of earned value to planned value.
= EV / PV
Target = 1; 0.95 - 1.05
Behind < 1 > Ahead
Under .90 and above 1.1 is bad

✔✔Estimate at Completion (EAC) - ✔✔= BAC / CPI
Project cost @ Completion if CPI is constant

Document information

Uploaded on
September 20, 2026
Number of pages
17
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$18.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
BOARDWALK
3.5
(41)
Sold
287
Followers
11
Items
36042
Last sold
1 week ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions