COSC 275 EXAM 2 QUESTIONS AND CORRECT ANSWERS
Correct 28
Incorrect 00
1 of 28
Term
Know how to find how deep grade beam excavation
Give this one a try later!
=Top of grade beam to bottom of =Subgrade elevation to bottom
void form (to bottom of beam if no of void form (to bottom of
void form) beam if no void form)
=Length of beam / spacing of stirrups,
round up and add 1
Don't know?
2 of 28
,Term
A steel membrane designation of W18x50 which is 20'-0" long weighs
Give this one a try later!
360 LBS 900 LBS
1000 lbs 500 lbs
Don't know?
3 of 28
Term
Insurance companies operate exactly like sureties
Give this one a try later!
true false
Don't know?
4 of 28
, Term
Rent expenses are NOT a direct project cost
Give this one a try later!
false true
Don't know?
5 of 28
Term
What estimating method was NOT presented in COSC275 this
semester?
Give this one a try later!
design-build integrated project delivery
CM agency cm at risk
Don't know?
Correct 28
Incorrect 00
1 of 28
Term
Know how to find how deep grade beam excavation
Give this one a try later!
=Top of grade beam to bottom of =Subgrade elevation to bottom
void form (to bottom of beam if no of void form (to bottom of
void form) beam if no void form)
=Length of beam / spacing of stirrups,
round up and add 1
Don't know?
2 of 28
,Term
A steel membrane designation of W18x50 which is 20'-0" long weighs
Give this one a try later!
360 LBS 900 LBS
1000 lbs 500 lbs
Don't know?
3 of 28
Term
Insurance companies operate exactly like sureties
Give this one a try later!
true false
Don't know?
4 of 28
, Term
Rent expenses are NOT a direct project cost
Give this one a try later!
false true
Don't know?
5 of 28
Term
What estimating method was NOT presented in COSC275 this
semester?
Give this one a try later!
design-build integrated project delivery
CM agency cm at risk
Don't know?