TCM 226- FINAL EXAM UPDATED ACTUAL QUESTIONS AND CORRECT ANSWERS

Document preview thumbnail
Preview 3 out of 18 pages

TCM 226- FINAL EXAM UPDATED ACTUAL QUESTIONS AND CORRECT ANSWERS Question: 1. What is the difference between Project Administration and Project Management? Answer: Project Admin. is a skill or steppingstone to PM. Project management is work related to managing the construction process Question: 2. What are some construction project admin skills? Answer:- procurement- construction operations- scheduling and coordination- material control- etc Question: 3. ______ works with diverse people to complete projects? Answer: Project Management Question: 4. True or False; Architects are responsible for performance? Answer: False, Project management is responsible Question: 5. What are some management techniques to achieve project goals and objectives Answer:- Organization of the project team- leadership- problem solving- reporting and record keeping- planning and scheduling Question: 6. why does the project need teamwork?

Content preview

TCM 226- FINAL EXAM UPDATED ACTUAL QUESTIONS
AND CORRECT ANSWERS

Question:
1. What is the difference between Project Administration and Project Management?
Answer:
Project Admin. is a skill or steppingstone to PM. Project management is work related to managing the
construction process

Question:
2. What are some construction project admin skills?
Answer:
- procurement
- construction operations
- scheduling and coordination
- material control
- etc

Question:
3. ______ works with diverse people to complete projects?
Answer:
Project Management

Question:
4. True or False; Architects are responsible for performance?
Answer:
False, Project management is responsible

Question:
5. What are some management techniques to achieve project goals and objectives
Answer:
- Organization of the project team
- leadership
- problem solving
- reporting and record keeping
- planning and scheduling

Question:
6. why does the project need teamwork?

,Answer:
- better communication
- increased productivity
- reduced project costs
- earlier project completion
- improved project team morale
- fewer claims and delays

Question:
7. Which of the follow is not a responsibility for an owner?
Answer:
resolve disputes/questions/ issues

Question:
8. true or false; A/E observes the work and has to be familiar with its progress
Answer:
true

Question:
9. Who provides dumpsters and portable toilets on a job?
Answer:
GC

Question:
10. what is AHJ?
Answer:
Authorities having Jurisdiction

Question:
11. True of False; The owner hires the AHJ
Answer:
False

Question:
12. Who requires the testing agency inspectors?
Answer:
AHJ, also required by code. A/E, owner, and contractor may also employ

Question:
13. Who hires the commissioning authority?
Answer:
Owner

Question:
14. Who is the communication between the owner and contractor?
Answer:
A/E

, Question:
15. Who is the communication between the subcontractor and A/E?
Answer:
GC

Question:
16. What does a Project Administration software help with?
Answer:
Cost control quality productivity safety scheduling construction documents

Question:
17. which is not a preconstruction activity?
Answer:
punch list

Question:
18. What is a Notice to proceed?
Answer:
a short document that directly tells contractor the specific project or portion of the project, for which the
work is to be accomplished

Question:
19. Who do you get the NTP from?
Answer:
Owner

Question:
20. Why do GC's subcontract?
Answer:
specialized work requires specialized labor & equipment, reduce risk

Question:
21. True or false; A buy-out is the process of awarding general contractors
Answer:
false

Question:
22. What is a Buy-out?
Answer:
The process of awarding subcontractors

Question:
23. What is a schedule of values?
Answer:
A list of how you will bill for your scope of work

Document information

Uploaded on
September 18, 2026
Number of pages
18
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$11.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Sold
70
Followers
2
Items
10505
Last sold
1 day ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions