A portfolio leader must choose between two initiatives.
Initiative A could deliver a moderate benefit in three months,
while Initiative B could deliver a potentially larger benefit in
,twelve months but carries significant uncertainty. Which SAFe
principle should most directly guide the decision?
A. Decentralize decision-making
B. Take an economic view
C. Organize around value
D. Assume variability; preserve options
Answer: B
Rationale: Taking an economic view means evaluating decisions
in their broader economic context rather than selecting work
solely because it promises the largest eventual benefit. Cost of
Delay, risk, development costs, operational considerations, and
timing all matter. The economically preferable decision may be
the one that delivers sufficient value sooner and reduces
exposure to uncertainty.
2.
A development organization frequently delays a valuable
feature because managers want every possible requirement
,finalized before development begins. What economic
consequence is most likely?
A. Reduced Cost of Delay
B. Increased opportunity cost and delayed value realization
C. Greater decentralization
D. Reduced variability
Answer: B
Rationale: Delaying delivery postpones the realization of
benefits and can increase Cost of Delay. In a rapidly changing
environment, waiting for complete certainty can also increase
the chance that the eventual solution no longer addresses the
most valuable customer need.
3.
A product owner is comparing two features. Feature X is easy to
build but produces little customer value. Feature Y is more
difficult but addresses a major customer problem and has
, significant time sensitivity. Which consideration is most
consistent with an economic view?
A. Select X because it has lower development effort
B. Select Y only if it has zero technical risk
C. Compare value, urgency, risk, and development cost
D. Select whichever feature has the shortest specification
Answer: C
Rationale: An economic view requires balancing multiple
economic factors. Development cost alone does not determine
the best decision. The organization should consider the expected
value, urgency or Cost of Delay, risk, and investment required.
4.
Why does Cost of Delay matter in Lean-Agile decision-making?
A. It measures the number of defects introduced by a team
B. It estimates the economic impact of delaying valuable work
C. It determines the team's velocity
D. It eliminates the need for prioritization