NACE AMPP CIP 2 – Questions With Right Solutions
Add to calendar
Play your way to mastery with fun games
Match Blocks Charms NEW
Practice questions for this set
Learn 1 /7 Study with Learn
Advise the coating applicator supervisor of your readings
Choose an answer
You are the NACE Coating Inspector on a tank lining project and are asked to perform a
high voltage holiday test after the coating applicators have completed their final repairs.
1 After meeting all the confined space entry permit you enter the tank and notice a very
strong odor of solvent.
Your first course of action should to:
, 2 In the event of a conflict between the Product Data Sheet and the Specification:
3 The Inspectors' goal at the Pre-Job Conference is to:
you are the NACY Coating Inspector on a tank lining project where desiccant
dehumidification is being used. Since the first shift of abrasive blasting your readings have
4 indicated relative humidity below 40%; however on the second shift of coating application
your readings are indicting 80%.
Your FIRST preferred course of action is to:
Don't know?
Terms in this set (102)
You are the NACE Coating Inspector Exit the tank and immediately and report the problem
on a tank lining project and are asked to the nearest safety supervisor
to perform a high voltage holiday test
after the coating applicators have
completed their final repairs. After
meeting all the confined space entry
permit you enter the tank and notice a
very strong odor of solvent.
Your first course of action should to:
You are working as an inspector in a A. Risk of chemical exposure
galvanizing plant for the first time. B. Risk of skin
What are some of the hazards you C. Risk of acid or caustic splashes
need to be aware of: D. a), b), and c)
Answer: D
, You are working as the only in-house Consult your supervisor
NACE Level 2 Inspector in a shop
setting when an independent 3rd party
NACE Level 3 Inspector, representing
the owner, presents you with a copy of
a Non Conformance Report (NCR) he
has written for a NACE2/SSPC SP 10
centrifugal blast which you had
previously approved.
Your FIRST preferred course of action
is to:
An Inspection and Test Plan is required It is always required
when:
The Inspectors' goal at the Pre-Job Obtain a clear understanding of the Specification
Conference is to:
Coating Surveys are legally required: On commercial marine vessels and offshore platforms
Individuals conducting Coating Always be trained and experienced Coating Industry
Surveys should:
The cost of qualified Coating Lower Coating Life Cycle Costs
Inspection is normally offset by:
You are a NACE Level 2 Coating Use a generally accepted industry standard and to
Inspector who has just arrived on a job take readings
in progress where there is no
Inspection and Test Plan (ITP). The first
morning you arrive the job is behind
schedule and you are asked to take
DIY Film Thickness readings.
Your FIRST preferred course of action
is to:
Add to calendar
Play your way to mastery with fun games
Match Blocks Charms NEW
Practice questions for this set
Learn 1 /7 Study with Learn
Advise the coating applicator supervisor of your readings
Choose an answer
You are the NACE Coating Inspector on a tank lining project and are asked to perform a
high voltage holiday test after the coating applicators have completed their final repairs.
1 After meeting all the confined space entry permit you enter the tank and notice a very
strong odor of solvent.
Your first course of action should to:
, 2 In the event of a conflict between the Product Data Sheet and the Specification:
3 The Inspectors' goal at the Pre-Job Conference is to:
you are the NACY Coating Inspector on a tank lining project where desiccant
dehumidification is being used. Since the first shift of abrasive blasting your readings have
4 indicated relative humidity below 40%; however on the second shift of coating application
your readings are indicting 80%.
Your FIRST preferred course of action is to:
Don't know?
Terms in this set (102)
You are the NACE Coating Inspector Exit the tank and immediately and report the problem
on a tank lining project and are asked to the nearest safety supervisor
to perform a high voltage holiday test
after the coating applicators have
completed their final repairs. After
meeting all the confined space entry
permit you enter the tank and notice a
very strong odor of solvent.
Your first course of action should to:
You are working as an inspector in a A. Risk of chemical exposure
galvanizing plant for the first time. B. Risk of skin
What are some of the hazards you C. Risk of acid or caustic splashes
need to be aware of: D. a), b), and c)
Answer: D
, You are working as the only in-house Consult your supervisor
NACE Level 2 Inspector in a shop
setting when an independent 3rd party
NACE Level 3 Inspector, representing
the owner, presents you with a copy of
a Non Conformance Report (NCR) he
has written for a NACE2/SSPC SP 10
centrifugal blast which you had
previously approved.
Your FIRST preferred course of action
is to:
An Inspection and Test Plan is required It is always required
when:
The Inspectors' goal at the Pre-Job Obtain a clear understanding of the Specification
Conference is to:
Coating Surveys are legally required: On commercial marine vessels and offshore platforms
Individuals conducting Coating Always be trained and experienced Coating Industry
Surveys should:
The cost of qualified Coating Lower Coating Life Cycle Costs
Inspection is normally offset by:
You are a NACE Level 2 Coating Use a generally accepted industry standard and to
Inspector who has just arrived on a job take readings
in progress where there is no
Inspection and Test Plan (ITP). The first
morning you arrive the job is behind
schedule and you are asked to take
DIY Film Thickness readings.
Your FIRST preferred course of action
is to: