Exchanges of information among all interested parties are encouraged: -
ANSWER-from release of the synopsis through receipt of proposals. FAR
15.201(a)
The process of examining and evaluating a proposed price without evaluating its
separate cost elements and proposed profit is called: - ANSWER-price analysis.
FAR 15.404-1(b)
,Which statement concerning requests for information (RFIs) is true? - ANSWER-
Responses to RFIs are not offers and may not be accepted by the government to
form a binding contract.FAR 15.201(e)
Which statement about proposal revisions is true? - ANSWER-The contracting
officer may request or allow proposal revisions to clarify or allow proposal
revisions to clarify and document understandings reached during negotiations.FAR
15.307(a),(b)
The contractor is required to submit certified cost and pricing data for
subcontractors that - ANSWER-are the lower of either $12,500,000 or valued at
more than both the pertinent cost or pricing threshold and more than 10% of the
prime contractor's price. FAR 404-3(c)(1)
Communication with an offeror for the sole purpose of eliminating minor
irregularities, informalities, or apparent clerical mistakes in the proposal is called -
ANSWER-clarification. FAR 15.306(a)(1), (2)
A proposal may be withdrawn - ANSWER-by written notice at any time before
award. FAR 15.208(e)
The extent of participation of small disadvantaged business concerns in
performance of the contract shall be evaluated in unrestricted acquisitions expected
to exceed - ANSWER-$650,000 ($1.5 million for construction) FAR 15.304(c)(4)
If defective pricing is discovered after award - ANSWER-the government is
entitled to a price adjustment if the amount is significant. FAR 15.407-1(b)(1)
Pre-award debriefings shall NOT disclose - ANSWER-the number of offerors.
FAR 15.505(e),(f)
,The least preferred method of submitting ideas/concepts to the government is -
ANSWER-unsolicited proposals. FAR 15.602, 15.604(a)(3)
When a contract is awarded, which part of the uniform contract format used for
solicitations, is not included in the contract? - ANSWER-Part IV-Representations
and Instructions. FAR 15.204-1
If any portion of a proposal received by the contracting officer electronically or by
facsimile is unreadable, the contracting officer - ANSWER-Shall permit the offeror
to resubmit the unreadable portion of the proposal using the method and time for
resubmission as prescribed by the contracting officer. FAR 15.207 (c)
Acceptable evidence to establish a proposal's time of receipt at the Government
installation includes - ANSWER-The time/date stamp of that installation on the
proposal wrapper; other documentary evidence of receipt maintained by the
installation; Oral testimony or statements of Government personnel. FAR
15.208(c)
The Contracting Officer shall amend a solicitation - ANSWER-When the
Government changes its requirements or terms and conditions. FAR 15.206(a)
Which statement concerning Oral Presentations by offerors as requested by the
government is true: - ANSWER-Oral presentations may substitute for, or augment,
written information. FAR 15.102
RFI are used by the Government to - ANSWER-Promote early exchanges of
information; Obtain price, delivery, and other market information for planning
purposes. FAR 15.201(c) & (e)
, The use of a uniform contract format facilitates preparation of the solicitation and
contract as well as reference to, and use of, those documents by - ANSWER-
Offerors, contractors, and contract administrators. FAR 15.204
Proposal revision is a change to a proposal made________ the solicitation closing
date, at the request of or as allowed by a __________, as the result of negotiations.
- ANSWER-after, contracting officer. FAR 15.001
For each attached document, exhibit and other attachment contained in Section J,
List of Attachments, the contracting officer shall list: - ANSWER-The title, date,
and number of pages. FAR 15.204-4
If any portion of a proposal received by the contracting officer electronically of by
facsimile is unreadable, the contracting officer immediately shall: - ANSWER-
Notify the offeror to resubmit the unreadable portion of the proposal. FAR
15.207(c)
A proposal may be withdrawn - ANSWER-By written notice at any time before
award. Orally before award if it is an oral proposal in response to oral solicitations.
FAR 15.403-1
The PCO shall not require submission of cost or pricing when: - ANSWER-Prices
agreed upon are based on adequate price competition. Prices agreed upon are based
on prices set by law or regulation; When a commercial item is being acquired.
FAR 15.403-1(b)
A certificate of Current Cost or Pricing data: - ANSWER-Does not constitute a
representation as to the accuracy of the contractor's judgment on the estimate of
future costs or projects. FAR 15.403-2(a), 15.406-2(b)