INTRODUCTION
This DAU PM Practitioner Certification Exam study guide compiles of the
most tested and latest questions with verified answers and detailed
rationales covering the Adaptive Acquisition Framework, program
management, cost estimating, earned value management, risk
management, test and evaluation, and acquisition documentation.
Designed for students and professionals at Defense Acquisition
University, it provides high-yield review for certification success. Each
question is paired with a concise rationale to reinforce understanding and
rapid recall.
Question 1
What is the primary intent of the Adaptive Acquisition Framework (AAF)?
A. To enforce a single, "one-size-fits-all" process for all DoD programs
B. To provide distinct pathways tailored to the specific nature and risk
profile of the capability being acquired
,C. To eliminate the need for Milestone Decision Authority (MDA) oversight
D. To mandate that all programs utilize Agile software development
Answer: B
Explanation: The AAF was designed to move away from a "one-size-
fits-all" approach, allowing program managers to select the pathway
that best fits their specific program needs. It recognizes that not all
defense systems are alike and offers tailored approaches based on
program characteristics.
Question 2
Which Adaptive Acquisition Framework (AAF) pathway is specifically
designed for rapid delivery of capabilities to fulfill urgent operational
needs in less than two years?
A. Major Capability Acquisition
B. Urgent Capability Acquisition
C. Defense Business Systems
D. Acquisition of Services
Answer: B
Explanation: Urgent Capability Acquisition addresses critical, time-
sensitive operational needs that require rapid delivery of
capabilities in less than two years. This pathway streamlines the
acquisition process to expedite fielding of urgently needed
capabilities.
,Question 3
Which AAF pathway is most suitable for acquiring rapidly evolving
software capabilities?
A. Major Capability Acquisition
B. Software Acquisition Pathway
C. Urgent Capabilities
D. Middle Tier of Acquisition
Answer: B
Explanation: The Software Acquisition Pathway is specifically
designed to deliver software capabilities quickly and iteratively,
accommodating rapid development cycles. It emphasizes modern
software development practices including Agile and DevSecOps.
Question 4
How many distinct pathways does the Adaptive Acquisition Framework
offer?
A. Three
B. Four
C. Five
D. Six
Answer: D
, Explanation: The AAF offers six distinct pathways: Major Capability
Acquisition, Urgent Capability Acquisition, Middle Tier of Acquisition,
Software Acquisition, Defense Business Systems, and Acquisition of
Services. Each pathway is tailored to specific types of capabilities
and risk profiles.
Question 5
What is the primary purpose of the Middle Tier of Acquisition (MTA)
pathway?
A. To acquire large, complex major defense acquisition programs
B. To rapidly develop and field prototypes or field production quantities
within five years
C. To acquire services for defense agencies
D. To manage defense business systems
Answer: B
Explanation: The MTA pathway is designed to rapidly develop and
field prototypes or field production quantities within five years. It is
intended for programs that can be executed faster than traditional
major capability acquisition.
Question 6
Which AAF pathway is designed for acquiring defense business systems?