Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Document preview thumbnail
Preview 4 out of 194 pages
Exam (elaborations)

UNDERGROUND_STORAGE_TANKS_EXAM_EXAM_SCRIPT_2026_FULL_SOLUTION_PRACTICE.pdf

Document preview thumbnail
Preview 4 out of 194 pages

UNDERGROUND_STORAGE_TANKS_EXAM_EXAM_SCRIPT_2026_FULL_SOLUTION_PRACTICE.pdf

Content preview

UNDERGROUND STORAGE TANKS
EXAM SCRIPT FULL SOLUTION

◉ An emergency impact valve (shear valve) is found in the following
location on an UST System.
a.) At the turbine piping termination
b.) Base of the dispenser
c.) Under the extractor tee
d.) Spill container. Answer: b.) Base of the dispenser


◉ Notification to perform a secondary containment test must be
given to the local agency by:
a.) A service technician or a licensed tank tester.
b.) Cathodic protection tester.
c.) Owner/operator of UST.
d.) State Water Resources Control Board.. Answer: c.)
Owner/operator of UST
CCR Title 23, Sec 2637(f)


◉ An owner or operator of an underground storage tank or any part
thereof that is destined for a specific reuse shall advise the local
agency, within the time frame specified by that agency, of all of the
following, except:

,a.) The nature of intended use
b.) The name of the new owner and new operator of the UST
c.) The location of intended use
d.) The State Water Resources Control Board must be advised not
the local agency. Answer: d.) The State Water Resources Control
Board must be advised not the local agency
CCR Title 23, Sec 2672(b)(4)


◉ Any person(s) installing underground storage tank systems or
components shall be certified or licensed by:
a.) The Contractors State License Board
b.) The local agency
c.) The State Water Resources Control Board
d.) The Regional Water Quality Board. Answer: a.) The Contractors
State License Board
CCR Title 23, Sec 2715(g)


◉ The designated UST operator(s) shall perform monthly visual
inspections of all UST's for which they are designated. The monthly
visual inspection shall include all of the following, except:
a.) Inspecting for the presence of hazardous substances, water, or
debris in spill containers.
b.) By July 1, 2005, verify that all facility employees have been
trained.

,c.) Reviewing the alarm history report or log for the previous month.
d.) Inspecting for the presence of hazardous substances, water, or
debris in containment sumps regardless of documentation showing
each alarm for the previous month has been responded to
appropriately.. Answer: d.) Inspecting for the presence of hazardous
substances, water, or debris in containment sumps regardless of
documentation showing each alarm for the previous month has been
responded to appropriately.
CCR Title 23, Sec 2715(c)


◉ The following statements are true about the certification of
monitoring equipment, except:
a.) The certification is an annual requirement.
b.) The certification shall be made on a "Monitoring System
Certification" form.
c.) UST owners and operators shall submit a completed
"Monitoring System Certification" form to the local agency
within 30 days after completion of the inspection.
d.) The "Monitoring System Certification" form must be posted..
Answer: d.) The "Monitoring System Certification" form must be
posted.
CCR Title 23, Sec 2638, 2641(j)


◉ Field-installed cathodic protection systems shall be designed and
certified as adequate by a:

, a.) Cathodic protection tester.
b.) A corrosion specialist.
c.) Owner/Operator.
d.) A service technician or a licensed tank tester.. Answer: b.) A
corrosion specialist
CCR Title 23, Sec 2635(a)(2)(A)


◉ A facility has a single wall tank and has chosen statistical
reconciliation plus tank integrity testing as their quantitative release
detection method. The following statements are false about this
method, except:
a.) A tank integrity test shall be conducted once every year.
b.) Statistical inventory reconciliation shall be conducted at least
once per month in accordance with section 2646.1.
c.) The SIR method shall be capable of detecting a release of 0.1
gallon per hour.
d.) The product level in the tank is at least 5 feet.. Answer: b.)
Statistical inventory reconciliation shall be conducted at least once
per month in accordance with section 2646.1.
CCR Title 23, Sec 2643(b)(3)


◉ The designated UST operator must train the employees about all
of the following, except:
a.) Permit conditions

Document information

Uploaded on
September 16, 2026
Number of pages
194
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$17.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Sold
1
Followers
0
Items
3365
Last sold
3 weeks ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions