CM 4211 1-4 Questions with Correct Answers (Grade A+)

Question 1: The Owner can specify in the contract how and what subcontractors can be sourced for the
project. (T/F)

Answer: True

Question 2: Select the best definition for General Contractor.
A. The Company that tells everyone on the project how and when to perform B. The company or individual
responsible for overseeing the construction process and managing any subcontractors, if applicable
C. The Company that performs the Front-End Loading and Engineering design

Answer: The company or individual responsible for overseeing the construction process and managing any
subcontractors, if applicable

Question 3: What are examples of contract documents?
A. Blueprints
B. Scope of Work
C. Design drawings
D. All of these answers
E. Technical specifications

Answer: D. All of these answers

Question 4: What is a Guaranteed Maximum Price contract?
A. The maximum amount the owner will have to pay the contractor is capped and is not to exceed
B. The maximum price the owner is to pay the vendors for materials and equipment
C. The maximum price the owner is to pay the subcontractor

Answer: A. The maximum amount the owner will have to pay the contractor is capped and is not to exceed

Question 5: What is a Design Bid contract?
A. A contract method that addresses design and construction costs simultaneously
B. A contract method that uses fast-tracking incentives as the basis of the contract
C. A contract method that bids after design

Answer: A. A contract method that addresses design and construction costs simultaneously

Question 6: A strong construction contract will outline the project's scope and leave little to no room
for which of the following.
A. Confusion on either side
B. Additional addendums
C. Red-line drawings

Answer: A. Confusion on either side


Page 1

,Question 7: Select the best definition for change request.
A. Describes how any requested changes will be communicated to the general contractor, as well as any fees
required for change orders and timelines for when changes can be requested and handled
B. A request for better working conditions and pay
C. A request for additional work

Answer: A. Describes how any requested changes will be communicated to the general contractor, as well
as any fees required for change orders and timelines for when changes can be requested and handled

Question 8: The right to subcontract any project work has to be outlined by which of the following.
Select all that apply.
A. The Prime Contractor
B. The contract
C. The Owner

Answer: B. The contract

Question 9: What is a Time and Materials contract?
A. The maximum price the owner is to pay the subcontractor
B. The maximum price the owner is to pay the vendors for materials and equipment
C. A contract that requires the client to pay the contractor for all labor and materials at a pre-negotiated rate

Answer: C. A contract that requires the client to pay the contractor for all labor and materials at a
pre-negotiated rate

Question 10: Of the three contracts LS, LSTK, and GMP, which once affords the most protection
financially and allows the owner to secure investors and loans?
A. GMP
B. All of these answers
C. LSTK
D. LS

Answer: A. GMP

Question 11: What are examples of construction contract clauses for escalation?
A. Fuel and gas
B. Steel
C. Construction materials and equipment
D. All of these answers

Answer: D. All of these answers




Page 2

, Question 12: What does Indemnification mean?
A. Holds the owner responsible for any injuries after the project is over
B. The responsibility of the contractor for any damages or loss incurred by the owner due to the work of the
contractor
C. Legal term to hold the owner responsible for Prime Contractor negligence

Answer: B. The responsibility of the contractor for any damages or loss incurred by the owner due to the
work of the contractor

Question 13: Select the best definition for labor and materials.
A. Specific to only construction and small business contracts
B. Only used in State and not Federal Contracting language
C. A contractor who is responsible for procuring the materials, as well as any costs associated with the labor
and materials needed to complete the work

Answer: C. A contractor who is responsible for procuring the materials, as well as any costs associated with
the labor and materials needed to complete the work

Question 14: The advantage of cost plus is that the Prime Contractor will incur a profit. (T/F)

Answer: True

Question 15: Timeline is defined by which of the following.
A. Finish Date
B. Start Date
C. Both

Answer: C. Both

Question 16: What is a Design Bid Build contract?
A. All of these answers
B. The process that saves the owner time and money by combining the design and construction
C. A traditional construction project delivery method that involves the completion of three distinct phases in
sequence
D. The maximum price the owner is to pay the vendors for materials and equipment

Answer: C. A traditional construction project delivery method that involves the completion of three distinct
phases in sequence

Question 17: What are examples of an Incentive construction contract?
A. Zero quality defects
B. Safety awards
C. All of these answers
D. Fast tracking

Answer: C. All of these answers


Page 3

Document information

Uploaded on
September 16, 2026
Number of pages
24
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$13.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
DrJon
3.8
(159)
Sold
594
Followers
188
Items
23698
Last sold
2 days ago




Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions