Question 1: Lecture 7
Answer: lecture 7
Question 2: "FOB Jobsite" means that the material supplier will deliver the materials?
Answer: true
Question 3: "FOB supply house" means that the sale is complete when the truck is loaded at the supply
house?
Answer: true
Question 4: "FOB" stands for "freight over board" ?
Answer: false
Question 5: A purchase order should be used when only a minor amount of work onsite is expected?
Answer: true
Question 6: Most conflicts on purchase orders have to do with the boilerplate provisions?
Answer: true
Question 7: Storage of materials should be a factor in the size of the material purchase order?
Answer: true
Question 8: A purchase order may be used for materials even before the construction contract is
signed?
Answer: true
Question 9: The contractor's purchase order should state that the provisions of the purchase order
control no matter what the supplier's quote or delivery tickets provide?
Answer: true
Question 10: A copy of the prime contract does not need to be given to a material supplier when using
flow-down language in the purchase order?
Answer: false
Page 1
, Question 11: The contractor is not allowed to include a "pay-when-paid" provision in a purchase
order?
Answer: false
Question 12: A purchase order should not be used for a trash pickup contract?
Answer: false
Question 13: A fabricator is usually considered a subcontractor and not a material supplier?
Answer: false
Question 14: If a third-party is used to transfer the materials from the supply house to the jobsite, then
the contractor will always be liable for transportation damages?
Answer: false
Question 15: Prices quoted by material suppliers may depend on the size of the order?
Answer: true
Question 16: A description of the materials being ordered may be provided by referring to a section of
the drawings and/or specifications and then providing the material supplier with those documents?
Answer: true
Question 17: It is important to know whether sales taxes are in the quote from the supplier?
Answer: true
Question 18: The contractor should not give a material supplier a project schedule?
Answer: false
Question 19: Shipping instructions should include where the materials are to be delivered?
Answer: true
Question 20: "2/10 net 30" means that the material supplier will give a 10% discount if the bill is paid
in full in 30 days?
Answer: false
Page 2
Question 1: Lecture 7
Answer: lecture 7
Question 2: "FOB Jobsite" means that the material supplier will deliver the materials?
Answer: true
Question 3: "FOB supply house" means that the sale is complete when the truck is loaded at the supply
house?
Answer: true
Question 4: "FOB" stands for "freight over board" ?
Answer: false
Question 5: A purchase order should be used when only a minor amount of work onsite is expected?
Answer: true
Question 6: Most conflicts on purchase orders have to do with the boilerplate provisions?
Answer: true
Question 7: Storage of materials should be a factor in the size of the material purchase order?
Answer: true
Question 8: A purchase order may be used for materials even before the construction contract is
signed?
Answer: true
Question 9: The contractor's purchase order should state that the provisions of the purchase order
control no matter what the supplier's quote or delivery tickets provide?
Answer: true
Question 10: A copy of the prime contract does not need to be given to a material supplier when using
flow-down language in the purchase order?
Answer: false
Page 1
, Question 11: The contractor is not allowed to include a "pay-when-paid" provision in a purchase
order?
Answer: false
Question 12: A purchase order should not be used for a trash pickup contract?
Answer: false
Question 13: A fabricator is usually considered a subcontractor and not a material supplier?
Answer: false
Question 14: If a third-party is used to transfer the materials from the supply house to the jobsite, then
the contractor will always be liable for transportation damages?
Answer: false
Question 15: Prices quoted by material suppliers may depend on the size of the order?
Answer: true
Question 16: A description of the materials being ordered may be provided by referring to a section of
the drawings and/or specifications and then providing the material supplier with those documents?
Answer: true
Question 17: It is important to know whether sales taxes are in the quote from the supplier?
Answer: true
Question 18: The contractor should not give a material supplier a project schedule?
Answer: false
Question 19: Shipping instructions should include where the materials are to be delivered?
Answer: true
Question 20: "2/10 net 30" means that the material supplier will give a 10% discount if the bill is paid
in full in 30 days?
Answer: false