,A project was authorized as an operational necessity to repair a design flaw in the date field on a
computer system that constrains the year number to two digits instead of permitting the year to be
indicated with four digits. During execution of the activity concerned with identifying the affected
, software, five relevant software modules were discovered that had not been included in the scope
baseline. The project team must adjust the baselines to include the omitted scope.
Which change management phase does this scenario describe?
a) Preparing for the change
b) Managing the change
c) Reinforcing the change
d) Upgrading the change - correct ans:a) Preparing for the change
A general contractor is managing a highway construction project that will repair a flood-damaged road.
The Department of Transportation offered an incentive fee if the repairs are completed early. Therefore,
the project manager has established a rewards and recognition program and has communicated this
program to the project team member. The project's recognition program will reward project team
members who add value by accelerating the project while maintaining its ability to deliver the
completed scope correctly.
Which change management phase does this scenario describe?
a) Preparing for the change
b) Managing the change
c) Reinforcing the change
d) Upgrading the change - correct ans:c) Reinforcing the change
A general contractor is managing a construction project that will add a new conference room to an
existing office building. The project was documented in a fixed-price contract that specified a completion
date. The contract includes a damages clause imposing a late completion penalty if the conference room
is not ready for use by the due date. One month into the implementation, the customer wants to modify
the room's lighting equipment. The requested change will delay the project's critical path by three
months.
Which process should be used to maintain the existing baseline?
Assessment Latest recent & frequently
tested exam with questions and verified
accurate solutions (detailed &
elaborated) GRADED A+
,A project was authorized as an operational necessity to repair a design flaw in the date field on a
computer system that constrains the year number to two digits instead of permitting the year to be
indicated with four digits. During execution of the activity concerned with identifying the affected
, software, five relevant software modules were discovered that had not been included in the scope
baseline. The project team must adjust the baselines to include the omitted scope.
Which change management phase does this scenario describe?
a) Preparing for the change
b) Managing the change
c) Reinforcing the change
d) Upgrading the change - correct ans:a) Preparing for the change
A general contractor is managing a highway construction project that will repair a flood-damaged road.
The Department of Transportation offered an incentive fee if the repairs are completed early. Therefore,
the project manager has established a rewards and recognition program and has communicated this
program to the project team member. The project's recognition program will reward project team
members who add value by accelerating the project while maintaining its ability to deliver the
completed scope correctly.
Which change management phase does this scenario describe?
a) Preparing for the change
b) Managing the change
c) Reinforcing the change
d) Upgrading the change - correct ans:c) Reinforcing the change
A general contractor is managing a construction project that will add a new conference room to an
existing office building. The project was documented in a fixed-price contract that specified a completion
date. The contract includes a damages clause imposing a late completion penalty if the conference room
is not ready for use by the due date. One month into the implementation, the customer wants to modify
the room's lighting equipment. The requested change will delay the project's critical path by three
months.
Which process should be used to maintain the existing baseline?